4122 N COLBATH AVE 91423

Certificate Information: 4122 N COLBATH AVE 91423

Application / Permit
22010-20000-01356
Plan Check / Job No.
B22VN03963
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 15'-4" X 16'-8" DETACHED TRELLIS PER ENGINEER
Permit Issued
Issued on 8/5/2022
Issuing Office
Valley
Current Status
CofO Corrected on 7/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/22/2022 JEROME MAGAT PALMA
Corrections Issued 3/22/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 6/25/2022 JEROME MAGAT PALMA
Plan Check Approved 7/5/2022 JEROME MAGAT PALMA
Building Plans Picked Up 7/7/2022 APPLICANT
Issued 8/5/2022 APPLICANT
CofO in Progress 5/13/2024 MISAEL ESPARZA
CofO Issued-Status Void 6/5/2024 RUBEN SALAS
Permit Finaled-Status Void 6/5/2024 RUBEN SALAS
Re-Activate Permit 7/9/2024 RUBEN SALAS
Permit Finaled 7/11/2024 RUBEN SALAS
CofO Corrected 7/11/2024 RUBEN SALAS
Permit Finaled 7/11/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 5/10/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 5/23/2022 ROBERT HUGHES

Contact Information

Contractor Meola Mark Construction & Remodeling Co; Lic. No.: 740748-B 8376 KENTLAND AVENUE      WEST HILLS, CA 91304
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/14/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/6/2023 Partial Approval MISAEL ESPARZA
Structural Steel Frame 8/4/2023 Approved MISAEL ESPARZA
Pre-Inspection 2/26/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/25/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/25/2024 Approved MISAEL ESPARZA
Final 4/25/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/25/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 4/25/2024 Not Required MISAEL ESPARZA
Smoke Detectors 4/25/2024 Corrections Issued MISAEL ESPARZA
Verify Sprinkler Sign Off 4/25/2024 Approved MISAEL ESPARZA
Final 5/8/2024 OK to Issue CofO MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/8/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 5/8/2024 Approved MISAEL ESPARZA