16829 W SHERMAN WAY 91406
Certificate Information: 16829 W SHERMAN WAY 91406
- Application / Permit
- 22010-20000-01336
- Plan Check / Job No.
- B22VN03920
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-Story ADU PER DETACHED ADU ORDINANCE
- Permit Issued
- Issued on 1/24/2023
- Issuing Office
- Current Status
- CofO Issued on 12/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | CARLOS MONTES |
| Corrections Issued | 4/2/2022 | CARLOS MONTES |
| Quality Review Completed | 4/4/2022 | LIPING TENG |
| Plan Check Approved | 1/23/2023 | CARLOS MONTES |
| Issued | 1/24/2023 | APPLICANT |
| CofO in Progress | 10/31/2023 | RAUL OLAGI |
| Permit Finaled | 12/1/2023 | RUBEN SALAS |
| Permit Finaled | 12/1/2023 | RUBEN SALAS |
| CofO Issued | 12/1/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2022 | CARLOS AGUILERA |
| Highway dedication | Cleared | 4/5/2022 | CARLOS AGUILERA |
| ZA Case | Cleared | 4/5/2022 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/6/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 7/29/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/4/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/8/2022 | CARLOS AGUILERA |
| Frnt yard landscape/Water mgmt | Cleared | 12/22/2022 | STEVEN WECHSLER |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Architect | Hefner,, Charles David; Lic. No.: NA23963 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/22/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 3/1/2023 | Partial Approval | RAUL OLAGI |
| Special/Order Compliance | 3/1/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 4/3/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/8/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/8/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 5/8/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/8/2023 | Corrections Issued | RAUL OLAGI |
| Shower Pan | 5/8/2023 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 5/11/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/11/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/11/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 5/11/2023 | Approved | RAUL OLAGI |
| Shower Pan | 5/11/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/17/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 5/17/2023 | Approved | DAVID ANDERSON |
| Insulation | 5/17/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 5/17/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 5/23/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/23/2023 | Approved | RAUL OLAGI |
| Final | 9/19/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/19/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 9/19/2023 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 9/19/2023 | Approved | KIRK SANDERS |
| Final | 10/30/2023 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 10/30/2023 | Approved | RAUL OLAGI |
| Service/Power Release | 10/30/2023 | Approved | RAUL OLAGI |