16829 W SHERMAN WAY 91406

Certificate Information: 16829 W SHERMAN WAY 91406

Application / Permit
22010-20000-01336
Plan Check / Job No.
B22VN03920
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-Story ADU PER DETACHED ADU ORDINANCE
Permit Issued
Issued on 1/24/2023
Issuing Office
Current Status
CofO Issued on 12/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 CARLOS MONTES
Corrections Issued 4/2/2022 CARLOS MONTES
Quality Review Completed 4/4/2022 LIPING TENG
Plan Check Approved 1/23/2023 CARLOS MONTES
Issued 1/24/2023 APPLICANT
CofO in Progress 10/31/2023 RAUL OLAGI
Permit Finaled 12/1/2023 RUBEN SALAS
Permit Finaled 12/1/2023 RUBEN SALAS
CofO Issued 12/1/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/5/2022 CARLOS AGUILERA
Highway dedication Cleared 4/5/2022 CARLOS AGUILERA
ZA Case Cleared 4/5/2022 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 4/6/2022 CARLOS AGUILERA
Sewer availability Cleared 4/6/2022 CARLOS AGUILERA
Construction near power lines Cleared 7/29/2022 RIDWAN HARDY
Low Impact Development Cleared 8/4/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 8/8/2022 CARLOS AGUILERA
Frnt yard landscape/Water mgmt Cleared 12/22/2022 STEVEN WECHSLER

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Architect Hefner,, Charles David; Lic. No.: NA23963       ,
Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/22/2023 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 3/1/2023 Partial Approval RAUL OLAGI
Special/Order Compliance 3/1/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 4/3/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/8/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/8/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 5/8/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/8/2023 Corrections Issued RAUL OLAGI
Shower Pan 5/8/2023 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 5/11/2023 Approved RAUL OLAGI
HVAC-Rough 5/11/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 5/11/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 5/11/2023 Approved RAUL OLAGI
Shower Pan 5/11/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/17/2023 Approved DAVID ANDERSON
Green Building Rough 5/17/2023 Approved DAVID ANDERSON
Insulation 5/17/2023 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 5/17/2023 Approved DAVID ANDERSON
Drywall Nailing 5/23/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 5/23/2023 Approved RAUL OLAGI
Final 9/19/2023 Corrections Issued KIRK SANDERS
Green Building Final 9/19/2023 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 9/19/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 9/19/2023 Approved KIRK SANDERS
Final 10/30/2023 OK to Issue CofO RAUL OLAGI
Green Building Final 10/30/2023 Approved RAUL OLAGI
Service/Power Release 10/30/2023 Approved RAUL OLAGI