6628 N BRENNAN AVE 91307
Certificate Information: 6628 N BRENNAN AVE 91307
- Application / Permit
- 22010-20000-01294
- Plan Check / Job No.
- B22VN03900
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan PROPOSED 1 STORY ADU PER WFPP AND PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Current Status
- CofO Issued on 6/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 4/18/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 4/24/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/13/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 7/18/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 7/25/2022 | CRYSTEL MAALOUF |
| Issued | 8/19/2022 | APPLICANT |
| CofO in Progress | 5/12/2023 | TROY SANDERS |
| Permit Finaled | 6/30/2023 | JOHN JANSON |
| CofO Issued | 6/30/2023 | JOHN JANSON |
| Permit Finaled | 6/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/19/2022 | CARLOS AGUILERA |
| Construction within easement | Cleared | 6/1/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 6/3/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/19/2022 | Partial Approval | TROY SANDERS |
| Sewer | 9/19/2022 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 9/27/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 9/27/2022 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 10/31/2022 | Approved | TROY SANDERS |
| Green Building Rough | 10/31/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 10/31/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/31/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 10/31/2022 | Approved | TROY SANDERS |
| Green Building Rough | 11/8/2022 | Approved | JESUS PINEDA |
| Insulation | 11/8/2022 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 11/8/2022 | Partial Approval | JESUS PINEDA |
| Insulation | 11/14/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 11/28/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 11/28/2022 | Not Ready for Inspection | TROY SANDERS |
| Shower Pan | 11/28/2022 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 12/7/2022 | Not Ready for Inspection | TROY SANDERS |
| Shower Pan | 12/7/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/16/2022 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Not Ready | TROY SANDERS |
| ELECTRICAL-Final | 5/4/2023 | Approved | TROY SANDERS |
| Final | 5/4/2023 | Corrections Issued | TROY SANDERS |
| Green Building Final | 5/4/2023 | Approved | TROY SANDERS |
| HVAC-Final | 5/4/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 5/4/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2023 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 5/4/2023 | Approved | TROY SANDERS |
| Smoke Detectors | 5/4/2023 | Approved | TROY SANDERS |
| Final | 5/12/2023 | OK to Issue CofO | TROY SANDERS |
| Service/Power Release | 5/12/2023 | Approved | TROY SANDERS |