6628 N BRENNAN AVE 91307

Certificate Information: 6628 N BRENNAN AVE 91307

Application / Permit
22010-20000-01294
Plan Check / Job No.
B22VN03900
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan PROPOSED 1 STORY ADU PER WFPP AND PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 8/19/2022
Issuing Office
Current Status
CofO Issued on 6/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 CRYSTEL MAALOUF
Corrections Issued 4/18/2022 CRYSTEL MAALOUF
Quality Review Completed 4/24/2022 HERNAN ARREOLA
Applicant returned to address corrections 6/13/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 7/18/2022 CRYSTEL MAALOUF
Plan Check Approved 7/25/2022 CRYSTEL MAALOUF
Issued 8/19/2022 APPLICANT
CofO in Progress 5/12/2023 TROY SANDERS
Permit Finaled 6/30/2023 JOHN JANSON
CofO Issued 6/30/2023 JOHN JANSON
Permit Finaled 6/30/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/18/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/19/2022 CARLOS AGUILERA
Sewer availability Cleared 4/19/2022 CARLOS AGUILERA
Construction within easement Cleared 6/1/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 6/3/2022 ABDULLAH SADOZAI

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/19/2022 Partial Approval TROY SANDERS
Sewer 9/19/2022 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 9/27/2022 Approved TROY SANDERS
Footing/Foundation/Slab 9/27/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 10/31/2022 Approved TROY SANDERS
ELECTRICAL-Rough 10/31/2022 Approved TROY SANDERS
Green Building Rough 10/31/2022 Not Ready for Inspection TROY SANDERS
HVAC-Rough 10/31/2022 Approved TROY SANDERS
PLUMBING-Rough 10/31/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 10/31/2022 Approved TROY SANDERS
Green Building Rough 11/8/2022 Approved JESUS PINEDA
Insulation 11/8/2022 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 11/8/2022 Partial Approval JESUS PINEDA
Insulation 11/14/2022 Approved MORRIS JACKSON
Drywall Nailing 11/28/2022 Approved TROY SANDERS
Interior/Exterior Lathing 11/28/2022 Not Ready for Inspection TROY SANDERS
Shower Pan 11/28/2022 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 12/7/2022 Not Ready for Inspection TROY SANDERS
Shower Pan 12/7/2022 Approved TROY SANDERS
Interior/Exterior Lathing 12/16/2022 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/22/2023 SGSOV Not Ready TROY SANDERS
ELECTRICAL-Final 5/4/2023 Approved TROY SANDERS
Final 5/4/2023 Corrections Issued TROY SANDERS
Green Building Final 5/4/2023 Approved TROY SANDERS
HVAC-Final 5/4/2023 Approved TROY SANDERS
PLUMBING-Final 5/4/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/4/2023 SGSOV Approved TROY SANDERS
Service/Power Release 5/4/2023 Approved TROY SANDERS
Smoke Detectors 5/4/2023 Approved TROY SANDERS
Final 5/12/2023 OK to Issue CofO TROY SANDERS
Service/Power Release 5/12/2023 Approved TROY SANDERS