10916 N CANBY AVE 91326

Certificate Information: 10916 N CANBY AVE 91326

Application / Permit
22010-20000-01284
Plan Check / Job No.
B22VN03840
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'-4" X 63'-2" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) ALL WORK PER ENGINEER
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 7/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/19/2022 DANIEL ABRAMYAN
Corrections Issued 3/19/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 6/27/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 7/11/2022 DANIEL ABRAMYAN
Plan Check Approved 7/14/2022 DANIEL ABRAMYAN
Issued 7/14/2022 APPLICANT
Building Plans Picked Up 7/18/2022 APPLICANT
CofO in Progress 6/26/2023 DAVID SCANTLIN
Permit Finaled 7/28/2023 JOHN JANSON
CofO Issued 7/28/2023 JOHN JANSON
Permit Finaled 7/28/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/31/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/7/2022 CARLOS AGUILERA
Sewer availability Cleared 4/7/2022 CARLOS AGUILERA
Low Impact Development Cleared 6/13/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/14/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 11/9/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 11/9/2022 Partial Approval JEFFREY PARD
Sewer 11/9/2022 Not Ready for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 11/22/2022 Conditional Approval JOHN KIDWELL
PLUMBING-Rough 11/22/2022 Partial Approval JOHN KIDWELL
Sewer 11/22/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 1/17/2023 Approved JOHN KIDWELL
HVAC-Rough 1/17/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/17/2023 Partial Approval JOHN KIDWELL
PLUMBING-Rough 1/17/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/20/2023 Approved JOHN KIDWELL
Green Building Rough 1/20/2023 Approved JOHN KIDWELL
Insulation 1/20/2023 Conditional Approval JOHN KIDWELL
Verify Sprinkler Sign Off 1/20/2023 Approved JOHN KIDWELL
Drywall Nailing 1/27/2023 Approved SEAN HAUPT
Shower Pan 1/27/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 2/6/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 4/6/2023 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/13/2023 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 5/8/2023 Corrections Issued JOHN KIDWELL
ELECTRICAL-Rough 5/8/2023 Approved JOHN KIDWELL
Final 6/16/2023 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 6/16/2023 Approved DAVID SCANTLIN
Green Building Final 6/16/2023 Approved DAVID SCANTLIN
HVAC-Final 6/16/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Approved DAVID SCANTLIN
Service/Power Release 6/16/2023 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 6/16/2023 Approved DAVID SCANTLIN
ELECTRICAL-Final 6/23/2023 Approved DAVID SCANTLIN
Final 6/23/2023 OK to Issue CofO DAVID SCANTLIN
PLUMBING-Final 6/23/2023 Approved DAVID SCANTLIN
Service/Power Release 6/23/2023 Approved DAVID SCANTLIN