8141 N HAZELTINE AVE 91402
Certificate Information: 8141 N HAZELTINE AVE 91402
- Application / Permit
- 22010-20000-01250
- Plan Check / Job No.
- B22VN03739
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan* NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT AT REAR OF LOT
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | PRANITA SHAH |
| Corrections Issued | 4/8/2022 | PRANITA SHAH |
| Quality Review Completed | 4/16/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/24/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 3/12/2023 | PRANITA SHAH |
| Plan Check Approved | 4/5/2023 | PRANITA SHAH |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 8/25/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
| CofO Issued | 8/27/2025 | RUBEN SALAS |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/6/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 8/3/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 8/5/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 1/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/13/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/13/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 10/13/2023 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/16/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/16/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 11/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 11/30/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/31/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/31/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 2/9/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/15/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 3/15/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 3/19/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/21/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 3/21/2024 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 3/21/2024 | Approved | GREGG CUMMINGS |
| Wood Frame | 3/21/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/26/2024 | Approved | KIRK SANDERS |
| Insulation | 4/9/2024 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/9/2024 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 4/16/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 5/16/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/16/2024 | Partial Approval | GREGG CUMMINGS |
| Sewer | 7/25/2024 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 7/25/2024 | Approved | GREGG CUMMINGS |
| Final | 7/24/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/24/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/24/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/24/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 7/24/2025 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 7/24/2025 | Approved | VINCENT HANLEY |
| Final | 8/22/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Service/Power Release | 8/22/2025 | Approved | OGANES TARAKHCHYAN |