13410 W HERRON ST 91342

Certificate Information: 13410 W HERRON ST 91342

Application / Permit
22010-20000-01237
Plan Check / Job No.
B22VN03708
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Proposed (N) two story ADU (1152SF) and (N) patio cover attached to (e) garage
Permit Issued
Issued on 12/27/2022
Issuing Office
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 JOE VO
Corrections Issued 5/22/2022 JOE VO
Quality Review Completed 6/16/2022 MICHAEL PEREZ
Plan Check Approved 12/19/2022 JOE VO
Issued 12/27/2022 APPLICANT
CofO in Progress 3/19/2024 KEVIN BERBERYAN
Permit Finaled 4/1/2024 DANIEL ORRANTE
CofO Issued 4/1/2024 DANIEL ORRANTE
Permit Finaled 4/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/16/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 6/17/2022 ROMAN GUTIERREZ
Sewer availability Cleared 6/17/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 9/15/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/15/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/6/2023 Partial Inspection ARAM AVEDISIAN
Underground Mechanical 2/27/2023 Not Ready for Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 2/28/2023 Not Ready for Inspection DAVID ANDERSON
Sewer 2/28/2023 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 3/3/2023 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 3/6/2023 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 3/6/2023 Partial Approval MATTHEW NELSON
Sewer 3/6/2023 Partial Approval MATTHEW NELSON
Underground Mechanical 3/6/2023 Not Ready for Inspection MATTHEW NELSON
Deputy Other (see comments) 3/14/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 4/7/2023 Approved ARAM AVEDISIAN
Sewer 4/7/2023 Approved ARAM AVEDISIAN
Deputy Other (see comments) 4/12/2023 Conditional Approval MICHAEL SMITH
Pre-Inspection 5/22/2023 Partial Inspection ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 7/10/2023 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Partial Approval DAVID MATSON
Green Building Rough 7/10/2023 Not Ready for Inspection DAVID MATSON
Pre-Inspection 7/10/2023 Partial Inspection DAVID MATSON
Wood Frame 7/10/2023 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved RAUL OLAGI
PLUMBING-Rough 8/2/2023 Conditional Approval MISAEL ESPARZA
HVAC-Rough 8/21/2023 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 8/24/2023 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 8/28/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 9/11/2023 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 9/11/2023 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 9/15/2023 Partial Inspection ROBERT GOLD
ELECTRICAL-Rough 9/15/2023 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/15/2023 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 9/15/2023 Approved KEVIN BERBERYAN
HVAC-Rough 9/15/2023 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 9/15/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/19/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 9/19/2023 Approved KEVIN BERBERYAN
Green Building Rough 9/19/2023 Approved KEVIN BERBERYAN
HVAC-Rough 9/19/2023 Approved KEVIN BERBERYAN
Insulation 9/25/2023 Approved KEVIN BERBERYAN
Drywall Nailing 10/16/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/19/2023 Approved KEVIN BERBERYAN
Shower Pan 10/19/2023 Approved KEVIN BERBERYAN
Underground Mechanical 12/11/2023 Approved KEVIN BERBERYAN
Underground Mechanical 1/16/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 2/20/2024 Not Ready for Inspection THOMAS FINNILA
Pre-Inspection 2/20/2024 Partial Inspection THOMAS FINNILA
HVAC-Final 2/26/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 2/26/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 3/1/2024 Approved KEVIN BERBERYAN
Final 3/1/2024 Conditional Approval KEVIN BERBERYAN
Green Building Final 3/1/2024 Approved KEVIN BERBERYAN
HVAC-Final 3/1/2024 Approved KEVIN BERBERYAN
PLUMBING-Final 3/1/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Not Required KEVIN BERBERYAN
Service/Power Release 3/1/2024 Approved KEVIN BERBERYAN
Smoke Detectors 3/1/2024 Approved KEVIN BERBERYAN
Final 3/19/2024 OK to Issue CofO KEVIN BERBERYAN