13410 W HERRON ST 91342
Certificate Information: 13410 W HERRON ST 91342
- Application / Permit
- 22010-20000-01237
- Plan Check / Job No.
- B22VN03708
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Proposed (N) two story ADU (1152SF) and (N) patio cover attached to (e) garage
- Permit Issued
- Issued on 12/27/2022
- Issuing Office
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2022 | JOE VO |
| Corrections Issued | 5/22/2022 | JOE VO |
| Quality Review Completed | 6/16/2022 | MICHAEL PEREZ |
| Plan Check Approved | 12/19/2022 | JOE VO |
| Issued | 12/27/2022 | APPLICANT |
| CofO in Progress | 3/19/2024 | KEVIN BERBERYAN |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
| CofO Issued | 4/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/17/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 9/15/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/6/2023 | Partial Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 2/27/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/28/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Sewer | 2/28/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 3/3/2023 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 3/6/2023 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/6/2023 | Partial Approval | MATTHEW NELSON |
| Sewer | 3/6/2023 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 3/6/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Other (see comments) | 3/14/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/7/2023 | Approved | ARAM AVEDISIAN |
| Sewer | 4/7/2023 | Approved | ARAM AVEDISIAN |
| Deputy Other (see comments) | 4/12/2023 | Conditional Approval | MICHAEL SMITH |
| Pre-Inspection | 5/22/2023 | Partial Inspection | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/10/2023 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | DAVID MATSON |
| Green Building Rough | 7/10/2023 | Not Ready for Inspection | DAVID MATSON |
| Pre-Inspection | 7/10/2023 | Partial Inspection | DAVID MATSON |
| Wood Frame | 7/10/2023 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 8/2/2023 | Conditional Approval | MISAEL ESPARZA |
| HVAC-Rough | 8/21/2023 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/24/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/28/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/11/2023 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 9/11/2023 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/15/2023 | Partial Inspection | ROBERT GOLD |
| ELECTRICAL-Rough | 9/15/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/15/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 9/15/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 9/15/2023 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/15/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/19/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/19/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 9/19/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 9/19/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 9/25/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 10/16/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/19/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 10/19/2023 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 12/11/2023 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 1/16/2024 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Inspection | 2/20/2024 | Partial Inspection | THOMAS FINNILA |
| HVAC-Final | 2/26/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 2/26/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 3/1/2024 | Approved | KEVIN BERBERYAN |
| Final | 3/1/2024 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Final | 3/1/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 3/1/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 3/1/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Not Required | KEVIN BERBERYAN |
| Service/Power Release | 3/1/2024 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 3/1/2024 | Approved | KEVIN BERBERYAN |
| Final | 3/19/2024 | OK to Issue CofO | KEVIN BERBERYAN |