13953 W COHASSET ST 91405

Certificate Information: 13953 W COHASSET ST 91405

Application / Permit
22010-20000-01235
Plan Check / Job No.
B22VN03705
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25'-9" X 34' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) W/ 27'-9" X 30'-7" 2-CAR GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/22/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 RAPHAEL ROSAS
Corrections Issued 4/14/2022 RAPHAEL ROSAS
Quality Review Completed 4/21/2022 STEVEN KIM
Building Plans Picked Up 4/21/2022 APPLICANT
Plan Check Approved 8/16/2022 RAPHAEL ROSAS
Issued 8/22/2022 APPLICANT
CofO in Progress 8/1/2023 GREGG CUMMINGS
CofO Issued 9/11/2023 RUBEN SALAS
Permit Finaled 9/11/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/15/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/19/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 7/1/2022 TINA MIRANDA
Low Impact Development Cleared 8/2/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 8/4/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 8/16/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/13/2022 Partial Approval WILLIAM WREN
Excavation/Setback/Form/Re-Bar 10/20/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 10/20/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Deputy Wood Construction 11/18/2022 Conditional Approval DAVID MATSON
Deputy Wood Construction 11/29/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 1/25/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 1/25/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 1/31/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 1/31/2023 Approved GREGG CUMMINGS
HVAC-Rough 1/31/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/9/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 2/9/2023 Approved CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 2/9/2023 Approved CHRISTOPHER DELLEFIELD
Wood Frame 2/9/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/21/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 2/21/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Insulation 2/28/2023 Approved GREGG CUMMINGS
Drywall Nailing 3/10/2023 Approved CHRISTOPHER DELLEFIELD
Gas Test 3/10/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Shower Pan 3/10/2023 Approved CHRISTOPHER DELLEFIELD
Gas Test 3/14/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/14/2023 Approved CHRISTOPHER DELLEFIELD
Sewer 4/28/2023 Approved GREGG CUMMINGS
Gas Test 5/12/2023 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 5/12/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Service/Power Release 5/12/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Underground Mechanical 5/12/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 5/24/2023 Not Ready for Inspection GREGG CUMMINGS
Service/Power Release 5/24/2023 Not Ready for Inspection GREGG CUMMINGS
Final 7/26/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 7/26/2023 Approved GREGG CUMMINGS
HVAC-Final 7/26/2023 Approved GREGG CUMMINGS
PLUMBING-Final 7/26/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved GREGG CUMMINGS
Service/Power Release 7/26/2023 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 7/26/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 7/31/2023 Approved GREGG CUMMINGS
Final 7/31/2023 OK to Issue CofO GREGG CUMMINGS
Service/Power Release 7/31/2023 Approved GREGG CUMMINGS