6914 N ALCOVE AVE 91605

Certificate Information: 6914 N ALCOVE AVE 91605

Application / Permit
22010-20000-01219
Plan Check / Job No.
B22VN03643
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19' X 33' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
CofO Issued on 8/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 SELLA BENYAMIN
Corrections Issued 4/14/2022 SELLA BENYAMIN
Quality Review Completed 5/3/2022 STEVEN KIM
Building Plans Picked Up 5/5/2022 APPLICANT
Plan Check Approved 7/8/2022 SELLA BENYAMIN
Issued 7/18/2022 APPLICANT
CofO in Progress 6/27/2024 OGANES TARAKHCHYAN
Permit Finaled 8/16/2024 DANIEL ORRANTE
CofO Issued 8/16/2024 DANIEL ORRANTE
Permit Finaled 8/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/19/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/21/2022 ROMAN GUTIERREZ
Sewer availability Cleared 4/21/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 5/23/2022 RIDWAN HARDY
Low Impact Development Cleared 6/22/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/23/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/2/2023 Approved KIRK SANDERS
Sewer 6/22/2023 No Access for Inspection KIRK SANDERS
Underground Mechanical 6/22/2023 No Access for Inspection KIRK SANDERS
Underground Mechanical 7/10/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 7/17/2023 Approved KIRK SANDERS
Underground Mechanical 7/17/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 9/26/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 9/26/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Not Ready for Inspection KIRK SANDERS
Green Building Rough 9/26/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 9/26/2023 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 9/26/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 10/4/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 10/4/2023 Corrections Issued KIRK SANDERS
Green Building Rough 10/4/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 10/4/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 10/4/2023 Not Ready for Inspection KIRK SANDERS
Deputy Wood Construction 10/12/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 10/19/2023 Not Ready for Inspection KIRK SANDERS
Deputy Wood Construction 10/19/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 10/19/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Approved KIRK SANDERS
Green Building Rough 10/19/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 10/19/2023 Approved KIRK SANDERS
Underground Mechanical 10/19/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 10/19/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 10/26/2023 Approved CHRISTOPHER ROJAS
Green Building Rough 10/26/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/26/2023 Partial Approval CHRISTOPHER ROJAS
HVAC-Final 10/31/2023 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 10/31/2023 Approved CHRISTOPHER ROJAS
Insulation 10/31/2023 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/8/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 11/28/2023 Partial Approval ROBERT GOLD
Shower Pan 11/28/2023 Approved ROBERT GOLD
Special/Order Compliance 12/20/2023 Approved JOSE AVILA
Special/Order Compliance 12/21/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 3/11/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 4/4/2024 Partial Inspection JOSE AVILA
Underground Mechanical 4/5/2024 Approved JOSE AVILA
ELECTRICAL-Final 6/6/2024 Corrections Issued SALVADOR MARTINEZ
Final 6/6/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 6/6/2024 Corrections Issued SALVADOR MARTINEZ
HVAC-Final 6/6/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 6/6/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 6/6/2024 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 6/6/2024 Corrections Issued SALVADOR MARTINEZ
Final 6/26/2024 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 6/26/2024 Approved OGANES TARAKHCHYAN
Service/Power Release 6/26/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 6/26/2024 Approved OGANES TARAKHCHYAN