17049 W CELTIC ST 91344

Certificate Information: 17049 W CELTIC ST 91344

Application / Permit
22010-20000-01214
Plan Check / Job No.
B22VN03630
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 4/11/2022
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2022 APPLICANT
Assigned to Plan Check Engineer 3/14/2022 DANIEL YIP
Corrections Issued 3/15/2022 DANIEL YIP
Plan Check Approved 4/5/2022 DANIEL YIP
Issued 4/11/2022 APPLICANT
CofO in Progress 12/20/2022 DAVID SCANTLIN
Permit Finaled 1/19/2023 JOHN JANSON
CofO Issued 1/19/2023 JOHN JANSON
Permit Finaled 1/19/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/21/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 3/21/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/29/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/29/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/26/2022 Corrections Issued DAVID SCANTLIN
Special/Order Compliance 4/26/2022 Corrections Issued DAVID SCANTLIN
Underground Mechanical 4/26/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 6/21/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Approved DAVID SCANTLIN
Footing/Foundation/Slab 6/21/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 6/21/2022 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 6/21/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 7/5/2022 Partial Approval KRISTEN CAUSEY
Shower Pan 7/5/2022 Approved KRISTEN CAUSEY
Insulation 7/11/2022 Corrections Issued KRISTEN CAUSEY
Drywall Nailing 8/1/2022 Partial Approval JUSTIN HAWLEY
Interior/Exterior Lathing 8/1/2022 Approved JUSTIN HAWLEY
HVAC-Rough 8/8/2022 Approved KRISTEN CAUSEY
HVAC-Final 10/27/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/16/2022 Approved DAVID SCANTLIN
Drywall Nailing 11/16/2022 Approved DAVID SCANTLIN
Final 11/16/2022 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved DAVID SCANTLIN
Service/Power Release 11/16/2022 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 11/16/2022 Approved DAVID SCANTLIN
Final 12/9/2022 Not Ready for Inspection STEVEN BACK
Service/Power Release 12/9/2022 Not Ready for Inspection STEVEN BACK
Final 12/16/2022 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 12/16/2022 Approved DAVID SCANTLIN