13567 W GAIN ST 91331

Certificate Information: 13567 W GAIN ST 91331

Application / Permit
22010-20000-01211
Plan Check / Job No.
B22VN03629
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU AT REAR OF LOT.
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 JOE VO
Corrections Issued 3/12/2022 JOE VO
Applicant returned to address corrections 4/29/2022 JOE VO
Plan Check Approved 5/13/2022 JOE VO
Issued 5/18/2022 APPLICANT
CofO in Progress 12/18/2023 MICHEL ABAJAN
Permit Finaled 3/18/2024 RUBEN SALAS
CofO Issued 3/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/17/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/18/2022 CARLOS AGUILERA
Sewer availability Cleared 3/18/2022 CARLOS AGUILERA
Construction near power lines Cleared 4/23/2022 RIDWAN HARDY
Low Impact Development Cleared 4/26/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 4/26/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2022 Partial Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 10/17/2022 Corrections Issued MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 10/25/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/9/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 11/9/2022 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 11/9/2022 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 11/9/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 11/9/2022 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 11/9/2022 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 12/16/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 1/23/2023 Corrections Issued JOHN COLEMAN
HVAC-Rough 1/23/2023 Approved JOHN COLEMAN
Wood Frame 1/23/2023 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 1/26/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/1/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/1/2023 Approved MICHEL ABAJAN
Green Building Rough 2/1/2023 Approved MICHEL ABAJAN
MERV13>=Rough 2/1/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 2/1/2023 Approved MICHEL ABAJAN
Underground Mechanical 2/14/2023 Approved MICHEL ABAJAN
Insulation 2/23/2023 Approved MICHEL ABAJAN
Drywall Nailing 3/15/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/28/2023 Approved MICHEL ABAJAN
Final 7/28/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 7/28/2023 Approved MICHEL ABAJAN
Green Building Final 7/28/2023 Approved MICHEL ABAJAN
HVAC-Final 7/28/2023 Approved MICHEL ABAJAN
MERV13>=Final 7/28/2023 Approved MICHEL ABAJAN
METHANE-Barrier 7/28/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 7/28/2023 Approved MICHEL ABAJAN
PLUMBING-Final 7/28/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 7/28/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 7/28/2023 Approved MICHEL ABAJAN
Final 8/17/2023 Corrections Issued MISAEL ESPARZA
Service/Power Release 8/17/2023 Not Ready for Inspection MISAEL ESPARZA
Final 9/6/2023 Corrections Issued MICHEL ABAJAN
Final 12/15/2023 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 12/15/2023 Approved MICHEL ABAJAN