10250 N ARLETA AVE 91331
Certificate Information: 10250 N ARLETA AVE 91331
- Application / Permit
- 22010-20000-01202
- Plan Check / Job No.
- B22VN03610
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY IRREGULAR SHAPED 30' X 34'-6" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP AND ENGINEERING
- Permit Issued
- Issued on 10/11/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/13/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 4/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/29/2022 | APPLICANT |
| Applicant returned to address corrections | 6/21/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 9/8/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 10/11/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/11/2022 | APPLICANT |
| CofO in Progress | 7/12/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 7/31/2023 | RUBEN SALAS |
| CofO Issued | 7/31/2023 | RUBEN SALAS |
| Permit Finaled | 7/31/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/21/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 9/27/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Valenzuela Pancho Construction; Lic. No.: 1067736-B | 544 ORANGE GROVE AVE SAN FERNANDO, CA 91340 |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 3/2/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 3/2/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/10/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/14/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 3/20/2023 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Rough | 3/20/2023 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 3/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 3/20/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/5/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/5/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/15/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/15/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 6/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 6/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 6/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/11/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/11/2023 | Approved | JENNIFER RABUCHIN |
| Final | 7/11/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 7/11/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/11/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/11/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 7/11/2023 | Not Required | JENNIFER RABUCHIN |
| Smoke Detectors | 7/11/2023 | Approved | JENNIFER RABUCHIN |