5826 N CORBIN AVE 91356
Certificate Information: 5826 N CORBIN AVE 91356
- Application / Permit
- 22010-20000-01135
- Plan Check / Job No.
- B22VN03592
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23'-6" X 41'-3" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINERING.
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | RAPHAEL ROSAS |
| Corrections Issued | 4/18/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 4/21/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/21/2022 | APPLICANT |
| Applicant returned to address corrections | 8/25/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 9/21/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 9/21/2022 | RAPHAEL ROSAS |
| Issued | 9/28/2022 | APPLICANT |
| CofO in Progress | 5/24/2024 | JON MCHUGH |
| CofO in Progress | 7/5/2024 | SEAN WIRCH |
| CofO Issued | 9/3/2024 | JOHN JANSON |
| Permit Finaled | 9/3/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/13/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 6/11/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 7/26/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 7/28/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 1/30/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 4/11/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 4/11/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 4/17/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 4/17/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 4/17/2023 | Corrections Issued | JON MCHUGH |
| Deputy Wood Construction | 4/19/2023 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 4/27/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 4/27/2023 | Approved | JON MCHUGH |
| Green Building Rough | 4/27/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 4/27/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 4/27/2023 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 4/27/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 5/19/2023 | Approved | SEAN WIRCH |
| Green Building Rough | 5/19/2023 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 5/19/2023 | Approved | SEAN WIRCH |
| Insulation | 5/30/2023 | Not Ready for Inspection | JEFFREY BULL |
| Interior/Exterior Lathing | 5/30/2023 | Partial Approval | JEFFREY BULL |
| Drywall Nailing | 6/5/2023 | Approved | JEFFREY BULL |
| Shower Pan | 6/15/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 6/30/2023 | Approved | MORRIS JACKSON |
| HVAC-Final | 9/5/2023 | Not Ready for Inspection | JON MCHUGH |
| Gas Test | 9/11/2023 | Partial Approval | JON MCHUGH |
| Sewer | 9/11/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 9/11/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 11/6/2023 | Corrections Issued | JON MCHUGH |
| Final | 11/6/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 11/6/2023 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 11/6/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 11/6/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 11/15/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 11/15/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 11/15/2023 | Corrections Issued | JON MCHUGH |
| Service/Power Release | 11/15/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 11/30/2023 | Not Ready for Inspection | JEFFREY PARD |
| Final | 11/30/2023 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 11/30/2023 | Not Ready for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 11/30/2023 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Final | 5/2/2024 | Approved | JON MCHUGH |
| Final | 5/2/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 5/2/2024 | Approved | JON MCHUGH |
| HVAC-Final | 5/2/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 5/2/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 5/2/2024 | Approved | JON MCHUGH |
| Final | 5/24/2024 | OK to Issue CofO | JON MCHUGH |