10384 W STRATHMORE DR 90024

Certificate Information: 10384 W STRATHMORE DR 90024

Application / Permit
22010-20000-01133
Plan Check / Job No.
B22VN03591
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREGULAR SHAPED 1-STORY 29'-0" X 25'-0", DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g) NFPA 13D FIRE SPRIKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/2/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 COLIN LOREDO
Corrections Issued 3/21/2022 COLIN LOREDO
Quality Review Completed 3/21/2022 OMID HEDAYAT
Building Plans Picked Up 3/21/2022 APPLICANT
Applicant returned to address corrections 12/13/2022 MARVEL DELACRUZ
Applicant returned to address corrections 1/20/2023 MARVEL DELACRUZ
Applicant returned to address corrections 1/30/2023 MARVEL DELACRUZ
Plan Check Approved 2/2/2023 MARVEL DELACRUZ
Issued 2/2/2023 APPLICANT
CofO in Progress 11/14/2025 DANIEL VERA
Permit Finaled 11/29/2025 RICHARD STEINBACH
CofO Issued 11/29/2025 RICHARD STEINBACH
Permit Finaled 11/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/13/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/15/2022 DINAH GARIN
Sewer availability Cleared 6/15/2022 DINAH GARIN
Low Impact Development Cleared 11/10/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/17/2022 DINAH GARIN
GPI Written Notices Cleared 12/13/2022 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 12/13/2022 COLIN LOREDO
Hold Cleared 8/15/2023 JEREMY CORONEL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/17/2023 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 9/26/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 10/3/2023 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 4/4/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 4/4/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 4/12/2024 Partial Approval STEPHANIE SWANSON
HVAC-Rough 4/12/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 4/12/2024 Approved STEPHANIE SWANSON
Shower Pan 4/12/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 5/3/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 5/3/2024 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Approved STEPHANIE SWANSON
Green Building Rough 5/3/2024 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 5/3/2024 Corrections Issued STEPHANIE SWANSON
Verify Sprinkler Sign Off 5/3/2024 Approved STEPHANIE SWANSON
HVAC-Rough 5/8/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 5/15/2024 Approved STEPHANIE SWANSON
Green Building Rough 5/15/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 5/15/2024 Partial Approval STEPHANIE SWANSON
Insulation 6/14/2024 Corrections Issued STEPHANIE SWANSON
Insulation 6/21/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 7/5/2024 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 7/16/2024 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 8/12/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 8/20/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 8/20/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 8/26/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 8/26/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 9/5/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 9/5/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 9/11/2025 Not Ready for Inspection SEAN HAUPT
HVAC-Final 9/11/2025 Approved SEAN HAUPT
PLUMBING-Final 9/11/2025 Corrections Issued SEAN HAUPT
Service/Power Release 9/11/2025 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Final 9/16/2025 Approved DANIEL VERA
HVAC-Final 9/16/2025 Approved DANIEL VERA
PLUMBING-Final 9/16/2025 Not Ready for Inspection DANIEL VERA
Service/Power Release 9/16/2025 Not Ready for Inspection DANIEL VERA
Final 10/30/2025 Conditional Approval DANIEL VERA
Green Building Final 10/30/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved DANIEL VERA
Service/Power Release 10/30/2025 Approved DANIEL VERA
Smoke Detectors 10/30/2025 Approved DANIEL VERA
Final 11/7/2025 Corrections Issued DANIEL VERA
Service/Power Release 11/7/2025 Not Ready for Inspection DANIEL VERA
Final 11/14/2025 OK to Issue CofO DANIEL VERA
PLUMBING-Final 11/14/2025 Approved DANIEL VERA
Service/Power Release 11/14/2025 Approved DANIEL VERA