4765 N LEMONA AVE 91403
Certificate Information: 4765 N LEMONA AVE 91403
- Application / Permit
- 22010-20000-01131
- Plan Check / Job No.
- B22VN03590
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 13' X 17'-6" PATIO COVER W/ POOL BATH (EXTERIOR ACCESS ONLY) PER ENGINEERING.
- Permit Issued
- Issued on 10/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | COLIN LOREDO |
| Corrections Issued | 3/21/2022 | COLIN LOREDO |
| Quality Review Completed | 3/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Applicant returned to address corrections | 8/29/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 9/30/2022 | RAPHAEL ROSAS |
| Issued | 10/3/2022 | APPLICANT |
| CofO in Progress | 7/29/2023 | JUAN VALENZUELA |
| CofO Issued | 9/18/2023 | RUBEN SALAS |
| Permit Finaled | 9/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2022 | CHRIS CHAHBAZ |
| Low Impact Development | Cleared | 5/18/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 5/18/2022 | CHRIS CHAHBAZ |
| Construction near power lines | Cleared | 8/29/2022 | JOHN BACON |
Contact Information
| Contractor | Nork Construction Inc; Lic. No.: 1058592-B | 17204 CHATSWORTH ST #10 GRANADA HILLS, CA 91344 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/13/2022 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/21/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/31/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 10/31/2022 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/31/2022 | Approved | THOMAS FINNILA |
| Insulation | 11/2/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/2/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 11/7/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/7/2022 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 11/9/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 11/9/2022 | Approved | CALEB MEISTER |
| Shower Pan | 11/9/2022 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 11/14/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 11/14/2022 | Approved | THOMAS FINNILA |
| Wood Frame | 11/14/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 6/20/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 6/20/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 6/26/2023 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Final | 6/26/2023 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/28/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 7/28/2023 | Approved | JUAN VALENZUELA |
| Final | 7/28/2023 | OK to Issue CofO | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/28/2023 | Approved | JUAN VALENZUELA |
| Green Building Final | 7/28/2023 | Approved | JUAN VALENZUELA |
| MERV13>=Final | 7/28/2023 | Approved | JUAN VALENZUELA |
| MERV13>=Rough | 7/28/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 7/28/2023 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 7/28/2023 | Approved | JUAN VALENZUELA |