7456 N CLEON AVE 91352

Certificate Information: 7456 N CLEON AVE 91352

Application / Permit
22010-20000-01119
Plan Check / Job No.
B22VN03537
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New detached 2-story ADU at rear of property per ordinance 186,481.
Permit Issued
Issued on 4/14/2023
Issuing Office
Current Status
CofO Issued on 7/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 MARCELA FRANQUEZ
Corrections Issued 4/6/2022 HELEN NGUYEN
Quality Review Completed 4/10/2022 HERNAN ARREOLA
Applicant returned to address corrections 10/4/2022 MARCELA FRANQUEZ
Applicant returned to address corrections 2/10/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 2/27/2023 MARCELA FRANQUEZ
Plan Check Approved 4/4/2023 MARCELA FRANQUEZ
Issued 4/14/2023 APPLICANT
CofO in Progress 6/13/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 7/25/2025 RUBEN SALAS
CofO Issued 7/25/2025 RUBEN SALAS
Permit Finaled 7/25/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/13/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 6/8/2022 LAVEON RIDER
Eng Process Fee Ord 176,300 Cleared 6/13/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/13/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 7/28/2022 RIDWAN HARDY
Low Impact Development Cleared 8/15/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/15/2022 JOSE DUARTE-DIAZ

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Architect Hefner,, Charles David; Lic. No.: NA23963       ,
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/19/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 9/19/2024 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 9/24/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/1/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/22/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/31/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 11/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/13/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/13/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 11/13/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 11/13/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 11/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 11/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 11/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 11/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 11/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 11/21/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 2/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 2/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 6/11/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 6/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/11/2025 Approved ROBERTO PALACIOS-LOPEZ