11262 W SHELDON ST 91352

Certificate Information: 11262 W SHELDON ST 91352

Application / Permit
22010-20000-01114
Plan Check / Job No.
B22VN03521
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New ADU NEW DETACHED ADU (968 SQ.FT)
Permit Issued
Issued on 8/23/2022
Issuing Office
Current Status
CofO Issued on 9/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 ZAW HAN
Corrections Issued 3/11/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 4/5/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 4/14/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 8/13/2022 ZAW HAN
Plan Check Approved 8/15/2022 ZAW HAN
Issued 8/23/2022 APPLICANT
CofO in Progress 8/11/2023 DAVID ANDERSON
Permit Finaled 9/22/2023 RUBEN SALAS
CofO Issued 9/22/2023 RUBEN SALAS
Permit Finaled 9/22/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/18/2022 CARLOS AGUILERA
CPC Cleared 3/18/2022 DANIEL CORONADO
Grading Pre-Inspection Cleared 3/18/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 3/21/2022 CARLOS AGUILERA
Sewer availability Cleared 3/21/2022 CARLOS AGUILERA
Construction near power lines Cleared 5/12/2022 WALTER RAMIREZ
Construction within easement Cleared 5/12/2022 WALTER RAMIREZ
Hydrant and Access approval Cleared 5/23/2022 KURT CORRAL
HPOZ Cleared 6/1/2022 SUKI GERSHENHORN
Low Impact Development Cleared 6/10/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/13/2022 CARLOS AGUILERA
Specific Plan Cleared 7/20/2022 PEGGY MALONE-BROWN
GPI Written Notices Cleared 8/15/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 2036 CREEK RD      KITTY HAWK, NC 27949

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/13/2022 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 10/13/2022 Partial Approval DAVID ANDERSON
Sewer 10/13/2022 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 10/21/2022 Not Ready for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 10/28/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 11/16/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 11/21/2022 Approved DAVID ANDERSON
Sewer 11/21/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 12/1/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 12/19/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 12/19/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 12/23/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Approved DAVID ANDERSON
Green Building Rough 12/23/2022 Approved DAVID ANDERSON
HVAC-Rough 12/23/2022 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 12/23/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/3/2023 Approved DAVID ANDERSON
Insulation 1/13/2023 Approved DAVID ANDERSON
Drywall Nailing 1/20/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/15/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved DAVID ANDERSON
Underground Mechanical 3/21/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 7/14/2023 Approved DAVID ANDERSON
Final 7/14/2023 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 7/14/2023 Approved DAVID ANDERSON
Green Building Final 7/14/2023 Approved DAVID ANDERSON
HVAC-Final 7/14/2023 Approved DAVID ANDERSON
PLUMBING-Final 7/14/2023 Approved DAVID ANDERSON
Service/Power Release 7/14/2023 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 7/14/2023 Not Ready for Inspection DAVID ANDERSON
Final 7/21/2023 Corrections Issued DAVID ANDERSON
Service/Power Release 7/21/2023 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 7/21/2023 Approved DAVID ANDERSON
Final 8/10/2023 OK to Issue CofO DAVID ANDERSON
Service/Power Release 8/10/2023 Approved DAVID ANDERSON