24104-24106 W HIGHLANDER ROAD 91307

Certificate Information: 24104-24106 W HIGHLANDER ROAD 91307

Application / Permit
22010-20000-01092
Plan Check / Job No.
B22VN03434
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert attached garage into an accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/26/2022
Issuing Office
Current Status
CofO Issued on 9/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 MONICA RAMIREZ
Corrections Issued 3/10/2022 MONICA RAMIREZ
Applicant returned to address corrections 4/5/2022 MONICA RAMIREZ
Plan Check Approved 4/8/2022 MONICA RAMIREZ
No Progress 4/28/2022 MONICA RAMIREZ
Plan Check Approved 7/14/2022 MONICA RAMIREZ
Issued 7/26/2022 APPLICANT
CofO in Progress 8/25/2023 CHRIS CHRISTENSEN
CofO Issued 9/14/2023 JOHN JANSON
Permit Finaled 9/14/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/17/2022 CARLOS AGUILERA
Sewer availability Cleared 3/17/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/21/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/18/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/21/2022 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/31/2022 Approved CHRIS CHRISTENSEN
Pre-Inspection 11/29/2022 Partial Approval CHRIS CHRISTENSEN
Special/Order Compliance 11/29/2022 Partial Inspection KRISTEN CAUSEY
Insulation 12/15/2022 Partial Inspection KRISTEN CAUSEY
Insulation 12/28/2022 Partial Inspection KRISTEN CAUSEY
Pre-Inspection 12/28/2022 Partial Inspection KRISTEN CAUSEY
Insulation 12/30/2022 Not Ready for Inspection KRISTEN CAUSEY
Pre-Inspection 12/30/2022 Corrections Issued KRISTEN CAUSEY
Insulation 1/30/2023 Not Ready for Inspection JESUS PINEDA
Drywall Nailing 2/27/2023 Partial Inspection JESUS PINEDA
Drywall Nailing 3/1/2023 Approved KRISTEN CAUSEY
Final 6/27/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 6/27/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 6/27/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 6/27/2023 Approved CHRIS CHRISTENSEN
Wood Frame 6/27/2023 Approved CHRIS CHRISTENSEN
Final 7/28/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/28/2023 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Final 8/17/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 8/17/2023 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Approved CHRIS CHRISTENSEN
Final 8/24/2023 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 8/24/2023 Approved CHRIS CHRISTENSEN