11319 N LOUISE AVE 91344

Certificate Information: 11319 N LOUISE AVE 91344

Application / Permit
22010-20000-01076
Plan Check / Job No.
B22VN03363
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. PROPOSED 2 STORY DETACHED ADU
Permit Issued
Issued on 7/22/2022
Issuing Office
Current Status
CofO Corrected on 9/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 CRYSTEL MAALOUF
Corrections Issued 4/7/2022 CRYSTEL MAALOUF
Quality Review Completed 4/10/2022 HERNAN ARREOLA
Applicant returned to address corrections 6/22/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 6/27/2022 CRYSTEL MAALOUF
Plan Check Approved 7/22/2022 CRYSTEL MAALOUF
Issued 7/22/2022 APPLICANT
CofO in Progress 8/17/2023 STEVEN BACK
CofO in Progress 8/18/2023 HORACE FULTZ
CofO in Progress 8/18/2023 STEVEN BACK
CofO Issued-Status Void 8/25/2023 JOHN JANSON
Permit Finaled-Status Void 8/25/2023 JOHN JANSON
Re-Activate Permit 9/11/2023 JOHN JANSON
Permit Finaled 9/11/2023 JOHN JANSON
CofO Corrected 9/11/2023 JOHN JANSON
Permit Finaled 9/11/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/13/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/14/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/14/2022 JOSE DUARTE-DIAZ
Watercourse Cleared 4/15/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 4/25/2022 KIRK LINKLATER
Construction near power lines Cleared 6/15/2022 RIDWAN HARDY
Low Impact Development Cleared 6/15/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/16/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 6/16/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 6/16/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 6/16/2022 JOSE DUARTE-DIAZ
GPI Written Notices Cleared 7/22/2022 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: NA67443       ,
Engineer Chiu,, Linda Rustandi; Lic. No.: C67433 4 SAN MARCO      ALISO VIEJO, CA 92656

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/2/2022 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 9/13/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 9/13/2022 Approved SEAN HAUPT
Wood Frame 10/6/2022 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved SEAN HAUPT
Gas Test 12/2/2022 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Corrections Issued STEVEN BACK
Pre-Inspection 12/5/2022 Corrections Issued STEVEN BACK
Underground Mechanical 12/5/2022 Partial Inspection STEVEN BACK
Pre-Inspection 12/6/2022 Corrections Issued STEVEN BACK
Deputy Wood Construction 12/15/2022 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 12/19/2022 Corrections Issued STEVEN BACK
Green Building Rough 12/19/2022 Not Ready for Inspection STEVEN BACK
Pre-Inspection 12/19/2022 Partial Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval STEVEN BACK
Shower Pan 12/27/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 12/30/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 12/30/2022 Approved STEVEN BACK
HVAC-Rough 12/30/2022 Approved STEVEN BACK
PLUMBING-Rough 12/30/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 2/16/2023 Approved STEVEN BACK
Green Building Rough 2/16/2023 Approved STEVEN BACK
Interior/Exterior Lathing 2/16/2023 Partial Approval STEVEN BACK
MERV13>=Rough 2/16/2023 Approved STEVEN BACK
Special/Order Compliance 2/16/2023 Partial Inspection MORRIS JACKSON
Insulation 2/21/2023 Approved STEVEN BACK
Interior/Exterior Lathing 2/21/2023 Approved STEVEN BACK
Drywall Nailing 3/2/2023 Approved STEVEN BACK
Interior/Exterior Lathing 3/6/2023 Partial Approval KRISTEN CAUSEY
Sewer 5/9/2023 Not Ready for Inspection JUSTIN HAWLEY
Sewer 5/12/2023 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved STEVEN BACK
Gas Test 6/2/2023 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 7/18/2023 Not Ready for Inspection STEVEN BACK
Final 7/18/2023 Corrections Issued STEVEN BACK
Gas Test 7/18/2023 Approved STEVEN BACK
Green Building Final 7/18/2023 Approved STEVEN BACK
HVAC-Final 7/18/2023 Approved STEVEN BACK
MERV13>=Final 7/18/2023 Approved STEVEN BACK
PLUMBING-Final 7/18/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Not Ready STEVEN BACK
Smoke Detectors 7/18/2023 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 8/17/2023 Approved STEVEN BACK
Final 8/17/2023 Partial Approval STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Approved STEVEN BACK
Smoke Detectors 8/17/2023 Approved STEVEN BACK
Final 8/18/2023 OK to Issue CofO STEVEN BACK
Service/Power Release 8/18/2023 Approved STEVEN BACK