11053 W VALERIO ST 91352
Certificate Information: 11053 W VALERIO ST 91352
- Application / Permit
- 22010-20000-01075
- Plan Check / Job No.
- B22VN03361
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY 31' 11" X 28' 5" ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 3/17/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| Plan Check Approved | 12/13/2022 | GURUNATH NESARAJAH |
| Issued | 1/12/2023 | APPLICANT |
| CofO in Progress | 3/26/2024 | JOHN COLEMAN |
| CofO Issued | 4/11/2024 | RUBEN SALAS |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 4/25/2022 | RIDWAN HARDY |
| Sewer availability | Cleared | 6/22/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/27/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/7/2022 | DAGOVERTO GUERRERO |
Contact Information
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/22/2023 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 5/16/2023 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/2/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 8/7/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 8/22/2023 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 9/11/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 9/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 9/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 9/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 9/12/2023 | Conditional Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 9/14/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 9/19/2023 | Corrections Issued | JOHN HAYES |
| Wood Frame | 9/19/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 10/16/2023 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/16/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 10/16/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/20/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/20/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 10/20/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/3/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | JOHN HAYES |
| Green Building Rough | 11/15/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/15/2023 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 11/15/2023 | Approved | JOHN HAYES |
| Insulation | 11/27/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/7/2023 | Approved | JOHN HAYES |
| Pre-Inspection | 12/7/2023 | Approved | JOHN HAYES |
| Final | 12/19/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/19/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 12/19/2023 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 12/19/2023 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 12/27/2023 | Approved | JOHN HAYES |
| Final | 1/24/2024 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Service/Power Release | 1/24/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 1/24/2024 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 1/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/27/2024 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 2/27/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 3/7/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 3/7/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/18/2024 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 3/18/2024 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 3/19/2024 | Approved | JOHN COLEMAN |
| Final | 3/26/2024 | OK to Issue CofO | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 3/26/2024 | Approved | JOHN COLEMAN |