8552 W HILLROSE ST 91040

Certificate Information: 8552 W HILLROSE ST 91040

Application / Permit
22010-20000-01071
Plan Check / Job No.
B22VN03358
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU2-story addition. NEW ADU OVER EXISTING DETACHED GARAGE STRUCTURE. (NFPA-13-D SPRINKLERS THROUGHTOUT)
Permit Issued
Issued on 4/29/2022
Issuing Office
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 CRYSTEL MAALOUF
Corrections Issued 4/7/2022 CRYSTEL MAALOUF
Quality Review Completed 4/10/2022 HERNAN ARREOLA
Plan Check Approved 4/29/2022 CRYSTEL MAALOUF
Issued 4/29/2022 APPLICANT
CofO in Progress 3/16/2023 WILLIAM WREN
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/21/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/21/2022 CARLOS AGUILERA
Sewer availability Cleared 4/21/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 4/22/2022 KIRK LINKLATER
Specific Plan Cleared 4/25/2022 SARAH HOUNSELL
GPI Written Notices Cleared 4/29/2022 SAI KHUM

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/20/2022 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 5/27/2022 No Access for Inspection MATTHEW NELSON
Footing/Foundation/Slab 6/2/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 8/15/2022 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 8/15/2022 Corrections Issued MATTHEW NELSON
Green Building Rough 8/15/2022 Approved MATTHEW NELSON
HVAC-Rough 8/15/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 9/2/2022 Approved MATTHEW NELSON
HVAC-Rough 9/2/2022 Approved MATTHEW NELSON
PLUMBING-Rough 9/2/2022 Approved MATTHEW NELSON
Wood Frame 9/2/2022 Partial Approval MATTHEW NELSON
Insulation 10/25/2022 Approved MATTHEW NELSON
Drywall Nailing 11/2/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/7/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/10/2023 Approved WILLIAM WREN
ELECTRICAL-Final 3/10/2023 Corrections Issued WILLIAM WREN
Final 3/10/2023 Corrections Issued WILLIAM WREN
Green Building Final 3/10/2023 Approved WILLIAM WREN
HVAC-Final 3/10/2023 Corrections Issued WILLIAM WREN
PLUMBING-Final 3/10/2023 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Not Ready WILLIAM WREN
Smoke Detectors 3/10/2023 Approved WILLIAM WREN
Final 3/15/2023 OK to Issue CofO WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/15/2023 SGSOV Approved WILLIAM WREN
Service/Power Release 3/15/2023 Approved WILLIAM WREN