17352 W KINGSBURY ST 91344

Certificate Information: 17352 W KINGSBURY ST 91344

Application / Permit
22010-20000-01058
Plan Check / Job No.
B22VN03334
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan* New Detached One Story ADU per ordinance.
Permit Issued
Issued on 9/7/2022
Issuing Office
Current Status
CofO Issued on 6/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2022 APPLICANT
Assigned to Plan Check Engineer 3/8/2022 FARSHAD ALIMOHAMADI
Corrections Issued 3/8/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 8/10/2022 FARSHAD ALIMOHAMADI
Issued 9/7/2022 APPLICANT
CofO in Progress 6/14/2023 DAVID SCANTLIN
Permit Finaled 6/23/2023 JOHN JANSON
CofO Issued 6/23/2023 JOHN JANSON
Permit Finaled 6/23/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/10/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/10/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/10/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 6/22/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/3/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Next Generation Builders; Lic. No.: 1069728-B       ,
Contractor Polymath Development Group Inc; Lic. No.: 1069728-B       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/13/2022 Approved JEFFREY BULL
PLUMBING-Rough 9/29/2022 Partial Approval JEFFREY PARD
Underground Mechanical 9/29/2022 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 10/5/2022 Conditional Approval JOHN KIDWELL
BUILDING-Rough-Frame 10/24/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 10/24/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Approved DAVID SCANTLIN
Green Building Rough 10/24/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 10/24/2022 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 10/24/2022 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 10/24/2022 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 10/24/2022 Approved DAVID SCANTLIN
HVAC-Rough 11/10/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 12/6/2022 Approved JOHN KIDWELL
Green Building Rough 12/6/2022 Approved JOHN KIDWELL
Insulation 12/6/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/6/2022 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 12/6/2022 Approved JOHN KIDWELL
Drywall Nailing 12/8/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/15/2022 Approved JUSTIN HAWLEY
Shower Pan 12/15/2022 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Not Ready DAVID SCANTLIN
Final 4/21/2023 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 4/21/2023 Approved DAVID SCANTLIN
Green Building Final 4/21/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved DAVID SCANTLIN
Service/Power Release 4/21/2023 Approved DAVID SCANTLIN
Smoke Detectors 4/21/2023 Approved DAVID SCANTLIN
Final 6/14/2023 OK to Issue CofO DAVID SCANTLIN