4803 1/4 N LOWELL AVE 91214
Certificate Information: 4803 1/4 N LOWELL AVE 91214
- Application / Permit
- 22010-20000-01036
- Plan Check / Job No.
- B22VN03258
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Existing accessory living quarter (473 SF) conversion to ADU per state law
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- CofO Issued on 7/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | CARLOS MONTES |
| Corrections Issued | 3/4/2022 | CARLOS MONTES |
| Plan Check Approved | 3/10/2022 | CARLOS MONTES |
| Issued | 3/10/2022 | APPLICANT |
| CofO in Progress | 5/11/2022 | MATTHEW NELSON |
| CofO Issued | 7/23/2022 | MICHAEL SMITH |
| Permit Finaled | 7/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/4/2022 | JOSE DUARTE-DIAZ |
| Address approval | Cleared | 3/7/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | JOSE DUARTE-DIAZ |
| Miscellaneous | Cleared | 3/8/2022 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/30/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 4/5/2022 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/8/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/8/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/28/2022 | Approved | MATTHEW NELSON |
| Final | 4/28/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 4/28/2022 | Approved | MATTHEW NELSON |
| Final | 5/5/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/5/2022 | SGSOV Not Ready | MATTHEW NELSON |
| ELECTRICAL-Final | 5/10/2022 | Approved | MATTHEW NELSON |
| Final | 5/10/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 5/10/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/10/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | MATTHEW NELSON |