6898 N VAN NOORD AVE 91605
Certificate Information: 6898 N VAN NOORD AVE 91605
- Application / Permit
- 22010-20000-00992
- Plan Check / Job No.
- B22VN03131
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT PER ORDINANCE LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- Issued on 8/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | PINANK PATEL |
| Corrections Issued | 3/27/2022 | PINANK PATEL |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Applicant returned to address corrections | 1/9/2023 | MADISON ODELL |
| Applicant returned to address corrections | 6/9/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/13/2025 | PINANK PATEL |
| Plan Check Approved | 5/13/2025 | PINANK PATEL |
| Issued | 8/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/5/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 6/15/2022 | KURT CORRAL |
| Construction near power lines | Cleared | 7/20/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/19/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/24/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/16/2023 | NIKKI ZULUETA |
| Miscellaneous | Cleared | 5/13/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Built To Perfection Inc; Lic. No.: 837987-B | 22222 SHERMAN WAY #202 CANOGA PARK, CA 91303 |
| Engineer | Coleman,, Carl Parker; Lic. No.: C30322 | 19531 HWY 18 APPLE VALLEY, CA 92307 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/6/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/10/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 10/15/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 10/28/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/17/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 12/17/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/17/2025 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 12/17/2025 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 12/17/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/22/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 12/22/2025 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 12/22/2025 | Approved | JACK KARGODORIAN |
| Insulation | 12/26/2025 | Approved | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 12/26/2025 | Approved | CHRISTOPHER MORFIN |
| BUILDING-Rough-Frame | 1/5/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Drywall Nailing | 1/5/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 1/5/2026 | Corrections Issued | KEVIN BERBERYAN |
| Drywall Nailing | 1/9/2026 | Conditional Approval | KEVIN BERBERYAN |
| Drywall Nailing | 1/14/2026 | Approved | KEVIN BERBERYAN |
| Sewer | 1/22/2026 | Approved | WAYNE REGESTER |