2256 S MANNING AVE 90064

Certificate Information: 2256 S MANNING AVE 90064

Application / Permit
22010-20000-00991
Plan Check / Job No.
B22VN03117
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ADU Checked per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d), and (g) (800sf over rfa allowed)
Permit Issued
Issued on 7/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 SUNMIN LEE
Corrections Issued 4/6/2022 SUNMIN LEE
Quality Review Completed 4/19/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/21/2022 APPLICANT
Applicant returned to address corrections 7/26/2022 SUNMIN LEE
Applicant returned to address corrections 11/15/2022 SUNMIN LEE
Plan Check Approved 7/13/2023 SUNMIN LEE
Issued 7/13/2023 APPLICANT
CofO in Progress 9/15/2025 DANIEL VERA
Permit Finaled 9/18/2025 RICHARD STEINBACH
CofO Issued 9/18/2025 RICHARD STEINBACH
Permit Finaled 9/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/9/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 6/9/2022 ABEL CASILLAS
Sewer availability Cleared 6/9/2022 ABEL CASILLAS
Roof/Waste drainage to street Cleared 10/31/2022 CINDY QI
Flood clearance Cleared 6/27/2023 SAMSON WONG
GPI Written Notices Cleared 7/13/2023 SUNMIN LEE
Grading Pre-Inspection Cleared 7/13/2023 SUNMIN LEE
Low Impact Development Cleared 7/13/2023 ORVAL HERNANDEZ-MARCI

Contact Information

Architect Farhad,, Farshid; Lic. No.: C19859 840 20TH ST. # 13      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,
Engineer Azarmy,, Cyrus; Lic. No.: L9404 4402 CHARLEMONT AVE      WOODLAND HILLS, CA 91364
Engineer Dallalzadeh,, Curesh; Lic. No.: M26425 1659 WELLESLEY AVE      LOS ANGELES, CA 90025
Engineer Kaligi,, Sean; Lic. No.: M37797 655 N CENTRAL AVE 17TH FL      GLENDALE, CA 91203
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/11/2023 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/11/2023 Not Ready for Inspection STEPHANIE SWANSON
METHANE-Subgrade 12/11/2023 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 12/11/2023 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/13/2023 Partial Approval STEPHANIE SWANSON
METHANE-Subgrade 12/13/2023 Approved STEPHANIE SWANSON
Deputy Methane Barrier 1/8/2024 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 1/11/2024 Approved STEPHANIE SWANSON
METHANE-Barrier 1/11/2024 Approved STEPHANIE SWANSON
PLUMBING-Rough 3/5/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 4/12/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 4/12/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Approved STEPHANIE SWANSON
HVAC-Rough 4/12/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 4/12/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 4/16/2024 Corrections Issued STEPHANIE SWANSON
FLOOD-Proofing Certificate 4/16/2024 Approved STEPHANIE SWANSON
HVAC-Rough 4/16/2024 Approved STEPHANIE SWANSON
METHANE-Rough 4/16/2024 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 4/16/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 4/29/2024 Corrections Issued MEL KHACHATOURIAN
Shower Pan 4/29/2024 Not Ready for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 5/1/2024 Approved STEPHANIE SWANSON
Shower Pan 5/1/2024 Approved STEPHANIE SWANSON
Insulation 5/7/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 5/7/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 5/14/2024 Approved STEPHANIE SWANSON
Drywall Nailing 5/14/2024 Approved STEPHANIE SWANSON
Green Building Rough 5/14/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 6/3/2025 Not Ready for Inspection DANIEL VERA
Gas Test 6/3/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 6/3/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 6/3/2025 Not Ready for Inspection DANIEL VERA
Service/Power Release 6/3/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 6/20/2025 Approved DANIEL VERA
Final 6/20/2025 Corrections Issued DANIEL VERA
Green Building Final 6/20/2025 Approved DANIEL VERA
HVAC-Final 6/20/2025 Approved DANIEL VERA
PLUMBING-Final 6/20/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Not Ready DANIEL VERA
Service/Power Release 6/20/2025 Not Ready for Inspection DANIEL VERA
Smoke Detectors 6/20/2025 Approved DANIEL VERA
Final 9/8/2025 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Approved DANIEL VERA
Service/Power Release 9/8/2025 Not Required DANIEL VERA
Final 9/12/2025 OK to Issue CofO DANIEL VERA