11938 W REDBANK ST 91352

Certificate Information: 11938 W REDBANK ST 91352

Application / Permit
22010-20000-00981
Plan Check / Job No.
B22VN03096
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
Permit Issued
Issued on 4/10/2023
Issuing Office
Valley
Current Status
Issued on 4/10/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 TROY DEGUZMAN
Corrections Issued 3/31/2022 TROY DEGUZMAN
Quality Review Completed 4/7/2022 OMID HEDAYAT
Building Plans Picked Up 4/11/2022 APPLICANT
Plan Check Approved 3/10/2023 NILOOFAR MEHRAIN
Issued 4/10/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/18/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/18/2022 CARLOS AGUILERA
Sewer availability Cleared 4/18/2022 CARLOS AGUILERA
ZI Cleared 5/1/2022 STEVEN WECHSLER
Construction near power lines Cleared 7/6/2022 TINA MIRANDA
Low Impact Development Cleared 11/28/2022 ROGELIO CORTES
Hydrant and Access approval Cleared 1/29/2023 KURT CORRAL
Roof/Waste drainage to street Cleared 2/8/2023 CARLOS AGUILERA
Green Code Cleared 3/10/2023 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/29/2024 Approved MATTHEW NELSON
Pre-Inspection 3/29/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/9/2024 Partial Approval MATTHEW NELSON
PLUMBING-Rough 4/9/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 4/29/2024 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 4/29/2024 Not Ready for Inspection MATTHEW NELSON
MERV13>=Rough 4/29/2024 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 4/29/2024 Not Ready for Inspection MATTHEW NELSON
Wood Frame 4/29/2024 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 7/24/2024 Approved MATTHEW NELSON
HVAC-Rough 7/24/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 7/24/2024 Approved MATTHEW NELSON
HVAC-Rough 7/29/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 10/17/2024 Approved MATTHEW NELSON
HVAC-Rough 10/17/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 11/7/2024 Conditional Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 11/7/2024 Approved MICHEL ABAJAN
MERV13>=Rough 11/7/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 11/7/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/20/2024 Approved MATTHEW NELSON
Insulation 11/20/2024 Approved MATTHEW NELSON
Drywall Nailing 12/2/2024 Approved MATTHEW NELSON
Shower Pan 12/23/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/1/2025 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 4/7/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 7/1/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 7/22/2025 Approved MATTHEW NELSON
Service/Power Release 7/22/2025 Not Ready for Inspection MATTHEW NELSON