6528 N FIRMAMENT AVE 91406
Certificate Information: 6528 N FIRMAMENT AVE 91406
- Application / Permit
- 22010-20000-00955
- Plan Check / Job No.
- B22VN02984
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 14'-1" X 18'-8" DETACHED PATIO COVER PER ENGINEERING
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Current Status
- CofO Issued on 6/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2022 | JENNIFER LEE |
| Corrections Issued | 3/2/2022 | JENNIFER LEE |
| Applicant returned to address corrections | 6/27/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 7/13/2022 | ALEC MOUSAKHANIAN |
| Issued | 7/14/2022 | APPLICANT |
| Building Plans Picked Up | 7/20/2022 | APPLICANT |
| CofO in Progress | 6/18/2025 | RYAN SALAZAR |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
| CofO Issued | 6/18/2025 | RUBEN SALAS |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/6/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/29/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/29/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/29/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/29/2022 | MEGAN GODINEZ |
| CPC | Cleared | 7/11/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | A To Z Construction Inc; Lic. No.: 988824-B | 22759 CAVALIER ST WOODLAND HILLS, CA 91364 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2022 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 8/17/2022 | Approved | RICHARD DOCKUS |
| Wood Frame | 9/13/2022 | Corrections Issued | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 9/21/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 9/21/2022 | Approved | JACK KARGODORIAN |
| Final | 11/28/2022 | Partial Approval | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 11/28/2022 | Approved | RYAN SALAZAR |
| Final | 6/20/2025 | OK to Issue CofO | RYAN SALAZAR |