1015 N DEXTER ST 90042
Certificate Information: 1015 N DEXTER ST 90042
- Application / Permit
- 22010-20000-00952
- Plan Check / Job No.
- B22VN02965
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRREGULAR SHAPED 27'-8" x 78'-5 1/2" TWO-STORY SINGLE FAMILY DWELLING WITH ATT. GARAGE AND TRELLIS. NFPA 13D FIRE SPRINKLERS REQ'D THROUGHOUT. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | COLIN LOREDO |
| Corrections Issued | 3/14/2022 | COLIN LOREDO |
| Quality Review Completed | 3/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Applicant returned to address corrections | 5/27/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 7/7/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 8/11/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 8/24/2022 | SEAN SHAHMIRI |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 1/30/2025 | THOMAS LOGRASSO |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
| CofO Issued | 2/2/2025 | DEROLD HAUFF |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2022 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2022 | WALLIE JONG |
| Disturb/Remove Protected Trees | Cleared | 4/22/2022 | ADALBERTO VERA |
| Sewer availability | Cleared | 5/12/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 7/6/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 7/14/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 7/14/2022 | COLIN LOREDO |
| Permit | Cleared | 7/29/2022 | CHRISTOPHER ROCHA |
| Trees in Parkway | Cleared | 7/29/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 8/12/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/16/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 120 W WILSON AVE 1550 GLENDALE, CA 91203 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/10/2023 | Partial Approval | SCOTT FINNILA |
| Special/Order Compliance | 4/10/2023 | Corrections Issued | SCOTT FINNILA |
| Special/Order Compliance | 4/26/2023 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 5/3/2023 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 5/3/2023 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 5/3/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/12/2023 | Conditional Approval | SCOTT FINNILA |
| Underground Mechanical | 5/12/2023 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/25/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | No Access for Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/5/2023 | No Access for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/5/2023 | No Access for Inspection | SCOTT FINNILA |
| Special/Order Compliance | 6/5/2023 | No Access for Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/21/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 6/23/2023 | Partial Approval | SCOTT FINNILA |
| Reinforced Concrete Frame | 6/23/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/12/2023 | Partial Inspection | SCOTT FINNILA |
| Masonry Wall/Backfill | 7/12/2023 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 7/21/2023 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 7/26/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/28/2023 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/1/2023 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 8/1/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/31/2023 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Partial Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 9/15/2023 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/27/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 9/28/2023 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/15/2023 | No Access for Inspection | SCOTT FINNILA |
| Green Building Rough | 11/15/2023 | No Access for Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 11/15/2023 | No Access for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 2/22/2024 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 2/22/2024 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 2/22/2024 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 2/22/2024 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/28/2024 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/28/2024 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Conditional Approval | SCOTT FINNILA |
| Green Building Rough | 3/28/2024 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 3/28/2024 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 3/28/2024 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 3/28/2024 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/4/2024 | Approved | SCOTT FINNILA |
| Green Building Rough | 4/4/2024 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 4/18/2024 | Partial Inspection | SCOTT FINNILA |
| Insulation | 5/9/2024 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 5/9/2024 | Partial Approval | JOSH MEISTER |
| Shower Pan | 5/9/2024 | Not Ready for Inspection | JOSH MEISTER |
| Insulation | 5/10/2024 | Conditional Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/10/2024 | Partial Approval | SCOTT FINNILA |
| Shower Pan | 5/10/2024 | Approved | SCOTT FINNILA |
| Drywall Nailing | 5/24/2024 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/24/2024 | Partial Approval | SCOTT FINNILA |
| Final | 10/31/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 12/2/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 12/4/2024 | Approved | THOMAS LOGRASSO |
| Final | 12/9/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/9/2024 | Approved | THOMAS LOGRASSO |
| Green Building Final | 12/9/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 12/9/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 12/9/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 12/16/2024 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 1/2/2025 | Approved | THOMAS LOGRASSO |
| Final | 1/30/2025 | OK to Issue CofO | THOMAS LOGRASSO |