21406 W CELES ST 91364

Certificate Information: 21406 W CELES ST 91364

Application / Permit
22010-20000-00938
Plan Check / Job No.
B22VN02945
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE INTO ADU PER CA GC 65852.2(e)(1)(A). NO SQ SF ADDED. ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 6/22/2022
Issuing Office
Current Status
CofO Issued on 6/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 VIVIAN LAO
Corrections Issued 3/4/2022 VIVIAN LAO
Applicant returned to address corrections 4/1/2022 VIVIAN LAO
Plan Check Approved 4/8/2022 VIVIAN LAO
Issued 6/22/2022 APPLICANT
CofO in Progress 6/6/2023 PETER FOLLING
Permit Finaled 6/7/2023 JOHN JANSON
CofO Issued 6/7/2023 JOHN JANSON
Permit Finaled 6/7/2023 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/10/2022 SERGIO VALENZUELA
Address approval Cleared 3/17/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/17/2022 CARLOS AGUILERA
Sewer availability Cleared 3/17/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/18/2022 CARLOS AGUILERA
Historic monument Cleared 4/4/2022 MELISSA JONES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2022 Not Ready for Inspection PETER FOLLING
Deputy Drilled-In Anchors 9/26/2022 No Access for Inspection PETER FOLLING
Excavation/Setback/Form/Re-Bar 9/27/2022 Approved PETER FOLLING
Footing/Foundation/Slab 9/27/2022 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Approved PETER FOLLING
Interior/Exterior Lathing 11/2/2022 Partial Approval MORRIS JACKSON
ELECTRICAL-Rough 11/21/2022 Approved PETER FOLLING
Sewer 11/21/2022 Not Ready for Inspection PETER FOLLING
Insulation 12/5/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 12/5/2022 Corrections Issued PETER FOLLING
Pre-Inspection 12/5/2022 Not Ready for Inspection PETER FOLLING
Smoke Detectors 12/5/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 12/8/2022 Approved PETER FOLLING
Green Building Rough 12/8/2022 Approved PETER FOLLING
HVAC-Rough 12/8/2022 Approved PETER FOLLING
PLUMBING-Rough 12/8/2022 Approved PETER FOLLING
Insulation 12/12/2022 Approved PETER FOLLING
Drywall Nailing 12/21/2022 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Not Ready PETER FOLLING
SGSOV-Seismic Gas S/O Valve 5/19/2023 SGSOV Not Ready PETER FOLLING
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Required JUSTIN HAWLEY
Final 5/31/2023 Corrections Issued PETER FOLLING
Green Building Final 5/31/2023 Approved PETER FOLLING
Smoke Detectors 5/31/2023 Approved PETER FOLLING
Final 6/5/2023 OK to Issue CofO PETER FOLLING