410 1/2 E 80TH ST 90003
Certificate Information: 410 1/2 E 80TH ST 90003
- Application / Permit
- 22010-20000-00936
- Plan Check / Job No.
- B22VN02939
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (ADU).
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Current Status
- CofO Issued on 4/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2022 | JOE VO |
| Corrections Issued | 3/3/2022 | JOE VO |
| Plan Check Approved | 3/16/2022 | JOE VO |
| No Progress | 5/2/2022 | JOE VO |
| Plan Check Approved | 5/2/2022 | JOE VO |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 12/1/2023 | MICHAEL LEWIS |
| No Progress | 12/1/2023 | DAVID FEILER |
| Permit Finaled | 4/9/2024 | DEROLD HAUFF |
| CofO Issued | 4/9/2024 | DEROLD HAUFF |
| Permit Finaled | 4/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/7/2022 | PHILLIP MUNGUIA |
| Address approval | Cleared | 3/10/2022 | WALLIE JONG |
| Sewer availability | Cleared | 3/10/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/4/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/4/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 9/7/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 12/23/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 12/23/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/12/2023 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 4/12/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/1/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 5/1/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/5/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Approved | MICHAEL LEWIS |
| Insulation | 5/25/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/16/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/20/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/30/2023 | Approved | MICHAEL LEWIS |
| Final | 10/30/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 10/30/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 10/30/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 10/30/2023 | Approved | MICHAEL LEWIS |
| Final | 11/16/2023 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | MICHAEL LEWIS |
| Final | 11/30/2023 | OK to Issue CofO | MICHAEL LEWIS |
| Special/Order Compliance | 12/8/2023 | Corrections Issued | MICHAEL LEWIS |