5232 N BECKFORD AVE 91356
Certificate Information: 5232 N BECKFORD AVE 91356
- Application / Permit
- 22010-20000-00935
- Plan Check / Job No.
- B22VN02938
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 16' X 25' REC ROOM W/ POOL BATH EXTERIOR ACCESS ONLY. ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- Current Status
- CofO Issued on 12/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2022 | RAPHAEL ROSAS |
| Corrections Issued | 3/2/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/3/2022 | APPLICANT |
| Plan Check Approved | 5/7/2022 | RAPHAEL ROSAS |
| Issued | 5/9/2022 | APPLICANT |
| CofO in Progress | 12/1/2022 | DAVID SANDOVAL |
| CofO Issued | 12/20/2022 | MICHAEL SMITH |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/19/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 5/7/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/29/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 6/29/2022 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 7/7/2022 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 7/12/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 8/12/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 8/12/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 8/19/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 8/19/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/19/2022 | Partial Approval | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 8/19/2022 | Approved | DAVID SANDOVAL |
| Insulation | 8/24/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 8/29/2022 | Approved | MORRIS JACKSON |
| Final | 10/31/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 10/31/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 10/31/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 10/31/2022 | Approved | DAVID SANDOVAL |
| Final | 12/1/2022 | OK to Issue CofO | DAVID SANDOVAL |