434 E 93RD ST 90003

Certificate Information: 434 E 93RD ST 90003

Application / Permit
22010-20000-00932
Plan Check / Job No.
B21VN18209
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) RECREATION ROOM TO 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 7/7/2022
Issuing Office
Current Status
CofO Issued on 6/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2022 APPLICANT
Assigned to Plan Check Engineer 2/25/2022 DANIEL YIP
Corrections Issued 2/25/2022 DANIEL YIP
Applicant returned to address corrections 4/13/2022 DANIEL YIP
Plan Check Approved 5/13/2022 DANIEL YIP
Issued 7/7/2022 APPLICANT
CofO in Progress 5/14/2026 ARTHUR NEGRETE
Permit Finaled 6/1/2026 ANSON MAGLASANG
CofO Issued 6/1/2026 ANSON MAGLASANG
Permit Finaled 6/1/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/23/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 3/23/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 3/23/2022 CHRISTOPHER ROCHA
Construction within easement Cleared 4/4/2022 TINA MIRANDA
Eng Process Fee Ord 176,300 Cleared 4/5/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/8/2022 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/30/2022 Corrections Issued ALIZAH MAYAGOITIA
Pre-Inspection 10/5/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/13/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/21/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 11/3/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 12/12/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 1/25/2023 Corrections Issued JOHN KLARIN
PLUMBING-Rough 1/25/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 1/25/2024 Corrections Issued JAMES CHAVEZ
HVAC-Rough 1/25/2024 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 2/1/2024 Approved JOHN KLARIN
HVAC-Rough 2/1/2024 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/15/2024 Approved BEN MOLSTAD
Drywall Nailing 3/15/2024 Approved BEN MOLSTAD
Final 3/15/2024 Corrections Issued BEN MOLSTAD
Green Building Final 3/15/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 3/15/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/15/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 3/15/2024 Corrections Issued BEN MOLSTAD
Green Building Final 10/4/2024 Not Ready for Inspection BARRY HACHE
Final 10/21/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Final 10/21/2024 Not Ready for Inspection ANTHONY EGSON
Grounding or Bonding 10/21/2024 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved ANTHONY EGSON
Smoke Detectors 10/21/2024 Approved ANTHONY EGSON
Final 11/18/2024 No Access for Inspection ANTHONY EGSON
Green Building Final 11/18/2024 No Access for Inspection ANTHONY EGSON
Final 12/12/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Final 12/12/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 5/13/2026 Approved ARTHUR NEGRETE
Final 5/13/2026 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 5/13/2026 Approved ARTHUR NEGRETE
HVAC-Final 5/13/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 5/13/2026 Approved ARTHUR NEGRETE