11936 W RATNER ST 91605
Certificate Information: 11936 W RATNER ST 91605
- Application / Permit
- 22010-20000-00914
- Plan Check / Job No.
- B22VN02855
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 40'-0"X41'-0"ACCESSORY LIVING QUARTERS . NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/9/2022
- Issuing Office
- Current Status
- CofO Issued on 7/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | COLIN LOREDO |
| Corrections Issued | 3/30/2022 | COLIN LOREDO |
| Quality Review Completed | 4/7/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/8/2022 | APPLICANT |
| Applicant returned to address corrections | 11/23/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 12/7/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/9/2022 | MOHAMMAD ESMAILI |
| Issued | 12/9/2022 | APPLICANT |
| CofO in Progress | 5/20/2024 | MATTHEW NELSON |
| CofO in Progress | 6/11/2024 | MATTHEW NELSON |
| CofO in Progress | 7/12/2024 | MATTHEW NELSON |
| Permit Finaled | 7/26/2024 | RUBEN SALAS |
| CofO Issued | 7/26/2024 | RUBEN SALAS |
| Permit Finaled | 7/26/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/20/2022 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 5/28/2022 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 7/1/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 9/23/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/27/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 12/15/2022 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 12/15/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/22/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/30/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Shower Pan | 1/30/2023 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/14/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/14/2023 | Approved | MATTHEW NELSON |
| Gas Test | 2/14/2023 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 2/14/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 2/14/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 2/14/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 2/14/2023 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 2/14/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/16/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/16/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/22/2023 | Approved | MATTHEW NELSON |
| Insulation | 2/24/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/28/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 5/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Service/Power Release | 5/23/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/15/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/15/2024 | Approved | MATTHEW NELSON |
| Final | 5/15/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/15/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 5/15/2024 | Approved | MATTHEW NELSON |
| HVAC-Final | 5/15/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/15/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 5/15/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 5/15/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/17/2024 | Approved | MATTHEW NELSON |
| Final | 5/17/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 5/17/2024 | Approved | MATTHEW NELSON |