1025 3/4 N NOLDEN ST 90042
Certificate Information: 1025 3/4 N NOLDEN ST 90042
- Application / Permit
- 22010-20000-00891
- Plan Check / Job No.
- B22VN02755
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 32' X 25' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 2/26/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| Plan Check Approved | 8/17/2023 | ALEC MOUSAKHANIAN |
| Issued | 8/17/2023 | APPLICANT |
| CofO in Progress | 4/27/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 5/1/2024 | DEROLD HAUFF |
| Permit Finaled | 5/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2023 | AMAAN MALIK |
| Grading Pre-Inspection | Cleared | 1/12/2023 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/24/2023 | AMAAN MALIK |
| Construction near power lines | Cleared | 4/27/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/26/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 7/2/2023 | HUGO LOPEZ |
| GPI Written Notices | Cleared | 8/17/2023 | ALEC MOUSAKHANIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/13/2023 | Approved | ROY SPAULDING |
| Underground Mechanical | 11/13/2023 | Not Ready for Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 11/16/2023 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 12/19/2023 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 12/19/2023 | Approved | ROY SPAULDING |
| HVAC-Rough | 12/19/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 12/19/2023 | Approved | ROY SPAULDING |
| Shower Pan | 12/19/2023 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 12/19/2023 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 12/27/2023 | Approved | ROY SPAULDING |
| Shower Pan | 12/27/2023 | Approved | ROY SPAULDING |
| Drywall Nailing | 1/11/2024 | Approved | AMY COLIN |
| Final | 3/18/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 3/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV No Gas | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/20/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 4/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/24/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 4/24/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/24/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/25/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |