10916 N ARLETA AVE 91345
Certificate Information: 10916 N ARLETA AVE 91345
- Application / Permit
- 22010-20000-00858
- Plan Check / Job No.
- B22VN02685
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR SHAPED 26'-3" x 26'-6" TWO-STORY DET ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | SEAN SHAHMIRI |
| Corrections Issued | 3/25/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 3/29/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Plan Check Approved | 2/27/2023 | SEAN SHAHMIRI |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 1/2/2024 | JENNIFER RABUCHIN |
| No Progress | 4/12/2024 | ROBERT GOLD |
| CofO in Progress | 4/12/2024 | ROBERT GOLD |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
| CofO Issued | 6/21/2024 | RUBEN SALAS |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/18/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 7/8/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 11/14/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/17/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 2/17/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/17/2023 | Partial Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 4/17/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/24/2023 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/24/2023 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 4/24/2023 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 4/24/2023 | Approved | MICHEL ABAJAN |
| Wood Frame | 5/17/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/13/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/13/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 6/23/2023 | Approved | JENNIFER RABUCHIN |
| Deputy Wood Construction | 7/5/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/10/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 7/18/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/18/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/27/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/27/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/27/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Final | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/26/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| Final | 12/19/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 12/19/2023 | Partial Inspection | JOHN COLEMAN |
| ELECTRICAL-Final | 12/27/2023 | Approved | JENNIFER RABUCHIN |
| Final | 12/27/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 12/27/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/27/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/27/2023 | Approved | JENNIFER RABUCHIN |
| Final | 1/3/2024 | OK to Issue CofO | JENNIFER RABUCHIN |