1442 E 48TH PL 1-3 90011
Certificate Information: 1442 E 48TH PL 1-3 90011
- Application / Permit
- 22010-20000-00846
- Plan Check / Job No.
- B21VN18207
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) 2-CAR ATTACHED GARAGE AT 1ST FLOOR TO ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(C) AND (E) DUPLEX AT 2ND FLOOR TO REMAIN
- Permit Issued
- Issued on 12/14/2022
- Issuing Office
- Current Status
- CofO Issued on 8/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | YOUNG KIM |
| Corrections Issued | 3/21/2022 | YOUNG KIM |
| Quality Review Completed | 3/23/2022 | SAI KHUM |
| Applicant returned to address corrections | 5/31/2022 | YOUNG KIM |
| Applicant returned to address corrections | 8/26/2022 | YOUNG KIM |
| Applicant returned to address corrections | 9/7/2022 | YOUNG KIM |
| Plan Check Approved | 10/5/2022 | YOUNG KIM |
| Issued | 12/14/2022 | APPLICANT |
| CofO in Progress | 7/19/2024 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 7/20/2024 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 8/5/2024 | DAVID FEILER |
| CofO in Progress | 8/22/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/22/2024 | RUBEN SALAS |
| CofO Issued | 8/22/2024 | RUBEN SALAS |
| Permit Finaled | 8/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/22/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2022 | AMAAN MALIK |
| Tenant Habitability Plan | Cleared | 9/1/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Son-Mex Construction; Lic. No.: 972982-B | , |
| Engineer | Mohazzab, Hosseinian, Hossein Jon; Lic. No.: S3760 | 5408 W 140TH ST HAWTHORNE, CA 90250 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/27/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 3/2/2023 | Partial Approval | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 3/30/2023 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 4/4/2023 | Conditional Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 9/7/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/7/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/7/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 9/13/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 10/20/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/26/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 5/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/17/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/18/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/19/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/22/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |