8660 N NORRIS AVE 91352

Certificate Information: 8660 N NORRIS AVE 91352

Application / Permit
22010-20000-00845
Plan Check / Job No.
B22VN02646
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan 1200 SQFT NEW ADU ADDITION TO (E) DETACHED ADU "COMPLY WITH DEPARTMENT ORDER effective date 07/19/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 6/22/2022
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 CRYSTEL MAALOUF
Corrections Issued 3/25/2022 CRYSTEL MAALOUF
Quality Review Completed 3/30/2022 SAI KHUM
Applicant returned to address corrections 4/15/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 4/21/2022 CRYSTEL MAALOUF
Plan Check Approved 6/22/2022 CRYSTEL MAALOUF
Issued 6/22/2022 APPLICANT
CofO in Progress 2/2/2023 DAVID ANDERSON
CofO Issued 3/4/2023 MICHAEL SMITH
Permit Finaled 3/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/4/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/5/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/5/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 4/21/2022 WALTER RAMIREZ
Low Impact Development Cleared 6/10/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 6/14/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/1/2022 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 8/9/2022 Approved DAVID ANDERSON
PLUMBING-Rough 8/22/2022 Partial Approval DAVID ANDERSON
Insulation 8/25/2022 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 9/22/2022 Approved DAVID ANDERSON
HVAC-Rough 9/22/2022 Approved DAVID ANDERSON
PLUMBING-Rough 9/22/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 9/27/2022 Approved DAVID ANDERSON
Insulation 9/30/2022 Approved DAVID ANDERSON
Drywall Nailing 10/5/2022 Approved DAVID ANDERSON
Shower Pan 10/5/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 1/27/2023 Approved DAVID ANDERSON
Final 1/27/2023 Corrections Issued DAVID ANDERSON
Green Building Final 1/27/2023 Approved DAVID ANDERSON
Green Building Rough 1/27/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 1/27/2023 Approved DAVID ANDERSON
Final 2/1/2023 OK to Issue CofO DAVID ANDERSON