1948 N REDESDALE AVE 90039
Certificate Information: 1948 N REDESDALE AVE 90039
- Application / Permit
- 22010-20000-00837
- Plan Check / Job No.
- B22VN02636
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 37'-8" x 96'-1" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE, ATT. OPEN TRELLIS, ATT. DECK, AND A BASEMENT; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 8/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | SEAN SHAHMIRI |
| Corrections Issued | 3/7/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 3/10/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Applicant returned to address corrections | 5/23/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 6/21/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 8/8/2022 | SEAN SHAHMIRI |
| Issued | 8/8/2022 | APPLICANT |
| CofO in Progress | 6/21/2024 | WILLIAM KUEHN |
| CofO Issued | 6/27/2024 | DEROLD HAUFF |
| Permit Finaled | 6/27/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| Address approval | Cleared | 3/23/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/23/2022 | TREVOR QUAN |
| Highway dedication | Cleared | 3/23/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 3/29/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 4/22/2022 | DWAYNE LAURENT |
| Trees in Parkway | Cleared | 6/2/2022 | ADALBERTO VERA |
| Construction near power lines | Cleared | 7/19/2022 | RIDWAN HARDY |
| Permit | Cleared | 7/26/2022 | ABEL CASILLAS |
| Low Impact Development | Cleared | 8/4/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gaprelian,, Armen; Lic. No.: GE2668 | 1719 BEN LOMOND DR GLENDALE, CA 91202 |
| Engineer | Mansuri,, Mehran; Lic. No.: C78614 | 14944 HESBY ST SHERMAN OAKS, CA 91403 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2022 | Approved | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 11/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 12/16/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Other (see comments) | 12/19/2022 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/21/2023 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 3/20/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Shotcrete | 3/24/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/30/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 4/11/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/19/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 4/21/2023 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 4/28/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/4/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 5/8/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/16/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 5/18/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/23/2023 | Approved | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 5/25/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 6/12/2023 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 7/20/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 7/20/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 8/25/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 9/28/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 9/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Sewer | 9/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 10/10/2023 | Conditional Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 10/10/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 10/13/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 10/17/2023 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 10/24/2023 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/24/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 10/24/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 10/24/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 10/31/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 11/3/2023 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/3/2023 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 11/8/2023 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 11/15/2023 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/15/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/20/2023 | Approved | THOMAS LOGRASSO |
| Sewer | 11/20/2023 | Approved | THOMAS LOGRASSO |
| Shower Pan | 11/20/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 2/15/2024 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 4/11/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 4/11/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 4/11/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 4/16/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/30/2024 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 4/30/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 4/30/2024 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 5/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 6/20/2024 | OK to Issue CofO | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | WILLIAM KUEHN |
| Service/Power Release | 6/20/2024 | Approved | WILLIAM KUEHN |
| Smoke Detectors | 6/20/2024 | Approved | WILLIAM KUEHN |