5330 S GRAND AVE 90037

Certificate Information: 5330 S GRAND AVE 90037

Application / Permit
22010-20000-00833
Plan Check / Job No.
B22VN02605
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Permit to Install one RADCO Approved Factory Built Housing ADU over a raised floor foundation per LADBS ADU Standard Plan ADU29. Factory Built Housing per RAD-31-1030.
Permit Issued
Issued on 5/20/2022
Issuing Office
Current Status
CofO Issued on 7/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/21/2022 JOE VO
Corrections Issued 2/22/2022 JOE VO
Applicant returned to address corrections 3/29/2022 JOE VO
Plan Check Approved 5/16/2022 JOE VO
Issued 5/20/2022 APPLICANT
CofO in Progress 7/5/2023 BRENDAN MORELLI
Permit Finaled 7/16/2023 DEROLD HAUFF
CofO Issued 7/16/2023 DEROLD HAUFF
Permit Finaled 7/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/25/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 2/25/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/1/2022 TREVOR QUAN
Sewer availability Cleared 3/1/2022 TREVOR QUAN
Construction near power lines Cleared 5/13/2022 RIDWAN HARDY

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 150 E 57TH ST      LOS ANGELES, CA 90011
Engineer Farish,, William Crawford; Lic. No.: C30123 19432 CASTLEWOOD CR      HUNTINGTON BEACH, CA 92648

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/4/2022 Approved JOAQUIN GREENOUGH
Sewer 8/4/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 8/4/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 10/19/2022 No Access for Inspection SHAVONNE ESPINOZA
Green Building Rough 10/19/2022 No Access for Inspection SHAVONNE ESPINOZA
MERV13>=Rough 10/19/2022 No Access for Inspection SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 10/19/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 10/25/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/25/2022 Approved ALEJANDRO DE ARTOLA
MERV13>=Rough 10/25/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 12/5/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/16/2023 Approved BRENDAN MORELLI
HVAC-Final 2/16/2023 Approved BRENDAN MORELLI
PLUMBING-Final 2/16/2023 Approved BRENDAN MORELLI
Service/Power Release 2/16/2023 Not Required BRENDAN MORELLI
Final 6/20/2023 OK to Issue CofO BRENDAN MORELLI
Footing/Foundation/Slab 6/20/2023 Approved BRENDAN MORELLI
Green Building Final 6/20/2023 Approved BRENDAN MORELLI
MERV13>=Final 6/20/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 6/20/2023 SGSOV Not Required BRENDAN MORELLI
Smoke Detectors 6/20/2023 Approved BRENDAN MORELLI