7924 N GENESTA AVE 91406

Certificate Information: 7924 N GENESTA AVE 91406

Application / Permit
22010-20000-00815
Plan Check / Job No.
B22VN02579
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21' X 31' TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 6/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 SELLA BENYAMIN
Corrections Issued 3/25/2022 SELLA BENYAMIN
Quality Review Completed 4/5/2022 STEVEN KIM
Building Plans Picked Up 4/6/2022 APPLICANT
Plan Check Approved 4/23/2022 SELLA BENYAMIN
Issued 5/2/2022 APPLICANT
CofO in Progress 5/30/2023 JUAN VALENZUELA
CofO Issued 6/5/2023 MICHAEL SMITH
Permit Finaled 6/5/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/1/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/2/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/2/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 4/6/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/14/2022 Not Ready for Inspection ALAN MORELOS
PLUMBING-Rough 6/14/2022 Partial Approval ALAN MORELOS
Excavation/Setback/Form/Re-Bar 6/17/2022 Approved ALAN MORELOS
Footing/Foundation/Slab 6/17/2022 Approved ALAN MORELOS
Pre-Inspection 6/17/2022 Partial Inspection DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 7/13/2022 Partial Approval ALAN MORELOS
Special/Order Compliance 7/13/2022 Corrections Issued ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Not Ready for Inspection ALAN MORELOS
Sewer 7/28/2022 Corrections Issued ALAN MORELOS
Underground Mechanical 7/28/2022 Approved ALAN MORELOS
Underground Mechanical 7/29/2022 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Corrections Issued RAUL OLAGI
Rough-Elec/Plmb/HVAC 10/3/2022 Corrections Issued ALAN MORELOS
BUILDING-Rough-Frame 10/11/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 10/11/2022 Approved RAUL OLAGI
HVAC-Rough 10/11/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 10/11/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Partial Approval ROBERT GOLD
HVAC-Rough 10/21/2022 Not Ready for Inspection ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Approved DAVID MATSON
HVAC-Rough 11/1/2022 Approved DAVID MATSON
BUILDING-Rough-Frame 11/3/2022 Approved DAVID MATSON
Green Building Rough 11/3/2022 Approved DAVID MATSON
Interior/Exterior Lathing 11/3/2022 Partial Approval DAVID MATSON
Verify Sprinkler Sign Off 11/3/2022 Approved DAVID MATSON
Insulation 11/18/2022 Corrections Issued ROBERT GOLD
Drywall Nailing 12/1/2022 Approved ROBERT GOLD
Insulation 12/1/2022 Approved ROBERT GOLD
Interior/Exterior Lathing 12/1/2022 Approved ROBERT GOLD
Shower Pan 12/1/2022 Approved ROBERT GOLD
Final 5/4/2023 Corrections Issued JUAN VALENZUELA
Green Building Final 5/4/2023 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 5/4/2023 SGSOV Approved JUAN VALENZUELA
Service/Power Release 5/4/2023 Corrections Issued JUAN VALENZUELA
Smoke Detectors 5/4/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 5/23/2023 Approved JUAN VALENZUELA
Final 5/23/2023 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 5/23/2023 Approved JUAN VALENZUELA
PLUMBING-Final 5/23/2023 Approved JUAN VALENZUELA
Service/Power Release 5/23/2023 Approved JUAN VALENZUELA