1916 S WESTGATE AVE 90025

Certificate Information: 1916 S WESTGATE AVE 90025

Application / Permit
22010-20000-00803
Plan Check / Job No.
B22VN02525
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 62'-5" X 38' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 SELLA BENYAMIN
Corrections Issued 3/8/2022 SELLA BENYAMIN
Quality Review Completed 3/10/2022 STEVEN KIM
Building Plans Picked Up 3/11/2022 APPLICANT
Plan Check Approved 8/26/2022 SELLA BENYAMIN
Issued 8/26/2022 APPLICANT
CofO in Progress 8/10/2024 MICHAEL PELHAM
Permit Finaled 8/14/2024 RICHARD STEINBACH
CofO Issued 8/14/2024 RICHARD STEINBACH
Permit Finaled 8/14/2024 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 4/18/2022 JENSON LEE
Trees in Parkway Cleared 4/27/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 5/11/2022 CINDY JOSSELYN
Eng Process Fee Ord 176,300 Cleared 5/26/2022 JENSON LEE
Sewer availability Cleared 5/26/2022 JENSON LEE
Low Impact Development Cleared 7/21/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/26/2022 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 15134 FRIAR ST      VAN NUYS, CA 91411

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/19/2023 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 5/31/2023 Approved JESUS PINEDA
Footing/Foundation/Slab 5/31/2023 Approved JESUS PINEDA
Deputy Reinf. Concrete 6/12/2023 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 6/15/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Partial Approval JEREMY TODD
Green Building Rough 7/7/2023 Not Ready for Inspection JEREMY TODD
Structural Steel Frame 7/7/2023 Not Ready for Inspection JEREMY TODD
Verify Sprinkler Sign Off 7/7/2023 Not Ready for Inspection JEREMY TODD
BUILDING-Rough-Frame 8/14/2023 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Partial Approval MEL KHACHATOURIAN
Green Building Rough 8/14/2023 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 8/14/2023 Not Ready for Inspection MEL KHACHATOURIAN
Wood Frame 8/14/2023 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Partial Inspection BEN MOLSTAD
Special/Order Compliance 8/22/2023 Partial Inspection BEN MOLSTAD
Deputy Wood Construction 8/24/2023 Conditional Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Corrections Issued JESUS PINEDA
PLUMBING-Rough 9/7/2023 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 9/12/2023 Approved BEN MOLSTAD
HVAC-Rough 9/12/2023 Corrections Issued BEN MOLSTAD
Shower Pan 9/18/2023 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 9/20/2023 Corrections Issued BEN MOLSTAD
Verify Sprinkler Sign Off 9/20/2023 Approved BEN MOLSTAD
Wood Frame 9/20/2023 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 9/26/2023 Approved CARLOS MATAMOROS
Shower Pan 9/26/2023 Not Ready for Inspection CARLOS MATAMOROS
Special/Order Compliance 9/26/2023 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 9/28/2023 Corrections Issued ARAM AVEDISIAN
Green Building Rough 9/28/2023 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 10/4/2023 Approved BEN MOLSTAD
Shower Pan 10/4/2023 Approved BEN MOLSTAD
BUILDING-Rough-Frame 10/6/2023 Not Ready for Inspection CLAYTON GRAHAM
Green Building Rough 10/6/2023 Not Ready for Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 10/13/2023 Corrections Issued BEN MOLSTAD
Green Building Rough 10/13/2023 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 10/18/2023 Corrections Issued STEPHANIE SWANSON
Green Building Rough 10/18/2023 Approved STEPHANIE SWANSON
Insulation 11/27/2023 Approved BEN MOLSTAD
Drywall Nailing 12/5/2023 Approved TEMISTOCLES CAAL
Service/Power Release 1/29/2024 Not Ready for Inspection MICHAEL PELHAM
ELECTRICAL-Final 2/28/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 3/19/2024 Approved CARLOS MATAMOROS
Service/Power Release 3/29/2024 Approved MICHAEL PELHAM
HVAC-Final 4/18/2024 Corrections Issued SEAN HAUPT
PLUMBING-Final 4/18/2024 Corrections Issued SEAN HAUPT
Special/Order Compliance 4/18/2024 Corrections Issued SEAN HAUPT
HVAC-Final 5/8/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 5/10/2024 No Access for Inspection HERBERT GIRON
PLUMBING-Final 5/14/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/31/2024 Approved KIRK SANDERS
Final 5/31/2024 Corrections Issued KIRK SANDERS
Green Building Final 5/31/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 5/31/2024 Approved KIRK SANDERS
Structural Steel Frame 5/31/2024 Approved KIRK SANDERS
Final 8/10/2024 OK to Issue CofO MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 8/10/2024 SGSOV Approved MICHAEL PELHAM