17711 W CORINTHIAN DR 91316
Certificate Information: 17711 W CORINTHIAN DR 91316
- Application / Permit
- 22010-20000-00802
- Plan Check / Job No.
- B22VN02522
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW DETACHED (13'-0"x19'-6"), 199.7 SQFT REC. ROOM W/FULL BATHROOM ACCESSED FROM THE OUTSIDE FOR POOL
- Permit Issued
- Issued on 9/6/2022
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | PETER MOSESIAN |
| Corrections Issued | 3/5/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/10/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Plan Check Approved | 9/6/2022 | PETER MOSESIAN |
| Issued | 9/6/2022 | APPLICANT |
| CofO in Progress | 12/21/2023 | SEAN HAUPT |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
| CofO Issued | 4/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/25/2022 | MICHAEL GILLISSIE |
| Low Impact Development | Cleared | 8/23/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/23/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Elia,, Victor Anthony; Lic. No.: C64803 | 40912 CARLENA LN TEMECULA, CA 92591 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/29/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 9/29/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 9/29/2022 | Partial Approval | SEAN HAUPT |
| Underground Mechanical | 9/29/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/17/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 10/17/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Wood Frame | 10/17/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Approved | DAVID SANDOVAL |
| Shower Pan | 12/9/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 1/3/2023 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 1/19/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 1/19/2023 | Approved | DAVID SANDOVAL |
| Green Building Rough | 1/19/2023 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 1/19/2023 | Partial Approval | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 1/19/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Drywall Nailing | 2/13/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/3/2023 | Approved | DAVID SANDOVAL |
| Special/Order Compliance | 3/3/2023 | Partial Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 12/12/2023 | Approved | SEAN HAUPT |
| Final | 12/12/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/12/2023 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 12/12/2023 | Not Required | SEAN HAUPT |
| Smoke Detectors | 12/12/2023 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 12/12/2023 | Approved | SEAN HAUPT |
| Final | 12/20/2023 | OK to Issue CofO | SEAN HAUPT |