13003 W ADDISON ST 91423

Certificate Information: 13003 W ADDISON ST 91423

Application / Permit
22010-20000-00800
Plan Check / Job No.
B22VN02519
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (46'-7"x20'-4"), 796 SQFT ADU W/NFPA 13D SPRINKLERS THROUGHOUT PER PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 8/25/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 PETER MOSESIAN
Corrections Issued 3/24/2022 PETER MOSESIAN
Quality Review Completed 3/29/2022 OMID HEDAYAT
Building Plans Picked Up 4/5/2022 APPLICANT
Plan Check Approved 8/24/2022 PETER MOSESIAN
Issued 8/25/2022 APPLICANT
CofO in Progress 10/28/2024 OGANES TARAKHCHYAN
Permit Finaled 11/12/2024 DANIEL ORRANTE
CofO Issued 11/12/2024 DANIEL ORRANTE
Permit Finaled 11/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/28/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/29/2022 MEGAN GODINEZ
Sewer availability Cleared 4/29/2022 MEGAN GODINEZ
Permit Cleared 5/19/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 7/8/2022 LAVEON RIDER
Low Impact Development Cleared 7/14/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/9/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/9/2023 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 6/20/2023 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 6/20/2023 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 6/21/2023 Approved KIRK SANDERS
Deputy Reinf. Concrete 6/22/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval DAVID MATSON
HVAC-Rough 10/25/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/27/2023 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 10/27/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/31/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/7/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Approved KIRK SANDERS
Green Building Rough 11/7/2023 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 11/7/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 11/14/2023 Approved KIRK SANDERS
Green Building Rough 11/14/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 11/14/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 11/30/2023 Approved JUAN VALENZUELA
Insulation 11/30/2023 Approved JUAN VALENZUELA
Drywall Nailing 12/5/2023 Not Ready for Inspection KIRK SANDERS
Insulation 12/5/2023 Approved KIRK SANDERS
Drywall Nailing 12/12/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 12/20/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Shower Pan 1/16/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 1/25/2024 Approved THOMAS FINNILA
Sewer 3/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 3/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 4/1/2024 Corrections Issued MISAEL ESPARZA
Sewer 4/1/2024 Corrections Issued MISAEL ESPARZA
Underground Mechanical 4/1/2024 Not Ready for Inspection MISAEL ESPARZA
Gas Test 4/3/2024 Approved SALVADOR MARTINEZ
Sewer 4/3/2024 Approved SALVADOR MARTINEZ
PLUMBING-Final 7/17/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 8/1/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 8/12/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 8/19/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 8/26/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 8/30/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 8/30/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 9/4/2024 Approved OGANES TARAKHCHYAN
Green Building Final 9/19/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/19/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 9/19/2024 Approved OGANES TARAKHCHYAN
Final 10/17/2024 Corrections Issued OGANES TARAKHCHYAN
Service/Power Release 10/17/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Final 10/25/2024 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 10/25/2024 Approved OGANES TARAKHCHYAN