13003 W ADDISON ST 91423
Certificate Information: 13003 W ADDISON ST 91423
- Application / Permit
- 22010-20000-00800
- Plan Check / Job No.
- B22VN02519
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED (46'-7"x20'-4"), 796 SQFT ADU W/NFPA 13D SPRINKLERS THROUGHOUT PER PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | PETER MOSESIAN |
| Corrections Issued | 3/24/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/29/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/5/2022 | APPLICANT |
| Plan Check Approved | 8/24/2022 | PETER MOSESIAN |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 10/28/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
| CofO Issued | 11/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/29/2022 | MEGAN GODINEZ |
| Permit | Cleared | 5/19/2022 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 7/8/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 7/14/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/9/2023 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 6/20/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 6/21/2023 | Approved | KIRK SANDERS |
| Deputy Reinf. Concrete | 6/22/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Partial Approval | DAVID MATSON |
| HVAC-Rough | 10/25/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/27/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/27/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/31/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/7/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 11/7/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 11/14/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 11/14/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/30/2023 | Approved | JUAN VALENZUELA |
| Insulation | 11/30/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 12/5/2023 | Not Ready for Inspection | KIRK SANDERS |
| Insulation | 12/5/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 12/12/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/20/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 1/16/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 1/25/2024 | Approved | THOMAS FINNILA |
| Sewer | 3/28/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/28/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 4/1/2024 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 4/1/2024 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 4/1/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 4/3/2024 | Approved | SALVADOR MARTINEZ |
| Sewer | 4/3/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 8/1/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 8/12/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 8/19/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 8/26/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/30/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 8/30/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/4/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 9/19/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/19/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 10/17/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Service/Power Release | 10/17/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 10/25/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Service/Power Release | 10/25/2024 | Approved | OGANES TARAKHCHYAN |