6902 W BECKETT ST 91042

Certificate Information: 6902 W BECKETT ST 91042

Application / Permit
22010-20000-00790
Plan Check / Job No.
B21VN18206
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT GARAGE TO ADU WITH ADDITION
Permit Issued
Issued on 8/2/2023
Issuing Office
Current Status
CofO Issued on 6/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 CRYSTEL MAALOUF
Corrections Issued 3/25/2022 CRYSTEL MAALOUF
Quality Review Completed 3/30/2022 SAI KHUM
Applicant returned to address corrections 9/27/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 10/25/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 5/3/2023 CRYSTEL MAALOUF
Plan Check Approved 7/31/2023 CRYSTEL MAALOUF
Issued 8/2/2023 APPLICANT
CofO in Progress 5/6/2026 NICHOLAS TROWBRIDGE
Permit Finaled 6/3/2026 RUBEN SALAS
CofO Issued 6/3/2026 RUBEN SALAS
Permit Finaled 6/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/4/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/5/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 6/30/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/16/2022 MEGAN GODINEZ
Private sewage disp. approval Cleared 6/5/2023 VASIL MIHALEV
GPI Written Notices Cleared 7/30/2023 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 7/30/2023 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/14/2023 Not Ready for Inspection WILLIAM WREN
Rough-Elec/Plmb/HVAC 8/18/2023 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 8/29/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/10/2023 Not Ready for Inspection WILLIAM WREN
Green Building Rough 10/10/2023 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Partial Approval WILLIAM WREN
HVAC-Rough 10/30/2023 Corrections Issued WILLIAM WREN
Pre-Inspection 10/30/2023 Corrections Issued WILLIAM WREN
Deputy Wood Construction 11/7/2023 Conditional Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Approved WILLIAM WREN
HVAC-Rough 12/8/2023 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 12/13/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 12/13/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 12/13/2023 Approved WILLIAM WREN
Sewer 12/18/2023 Approved WILLIAM WREN
Underground Mechanical 12/18/2023 Approved WILLIAM WREN
Insulation 12/27/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 12/27/2023 Approved WILLIAM WREN
Drywall Nailing 1/4/2024 Approved THOMAS FINNILA
HVAC-Rough 1/25/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/16/2025 Approved WILLIAM WREN
Final 6/16/2025 Not Ready for Inspection WILLIAM WREN
Green Building Final 6/16/2025 Not Ready for Inspection WILLIAM WREN
Green Building Rough 6/16/2025 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Ready WILLIAM WREN
Smoke Detectors 6/16/2025 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 6/18/2025 Approved WILLIAM WREN
Final 6/18/2025 Corrections Issued WILLIAM WREN
Green Building Final 6/18/2025 Approved WILLIAM WREN
Green Building Rough 6/18/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Approved WILLIAM WREN
Smoke Detectors 6/18/2025 Approved WILLIAM WREN
Special/Order Compliance 11/25/2025 Partial Inspection DAVID MATSON
Final 4/6/2026 Conditional Approval NICHOLAS TROWBRIDGE
ELECTRICAL-Final 4/30/2026 No Access for Inspection MICHAEL CORTEZ
Final 4/30/2026 No Access for Inspection MICHAEL CORTEZ
Final 5/5/2026 OK to Issue CofO NICHOLAS TROWBRIDGE