10047 N BURNET AVE 91345
Certificate Information: 10047 N BURNET AVE 91345
- Application / Permit
- 22010-20000-00787
- Plan Check / Job No.
- B22VN02502
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* ADD 14' X 18'-2" TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/8/2022
- Issuing Office
- Current Status
- Issued on 7/8/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | SELLA BENYAMIN |
| Corrections Issued | 2/21/2022 | SELLA BENYAMIN |
| Plan Check Approved | 6/23/2022 | SELLA BENYAMIN |
| Issued | 7/8/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 2/23/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 5/24/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 6/1/2022 | RIDWAN HARDY |
| Hold | Cleared | 7/8/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 7/15/2022 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 8/23/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 9/2/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/6/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/6/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/13/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/19/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 10/24/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 10/24/2022 | Approved | JENNIFER RABUCHIN |
| Masonry Wall/Backfill | 10/24/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Drywall Nailing | 10/27/2022 | Approved | JENNIFER RABUCHIN |
| Sewer | 10/27/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 10/27/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Shower Pan | 11/8/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/17/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/9/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/9/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/9/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/9/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 2/9/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 2/9/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 2/9/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/9/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 2/9/2023 | Approved | JENNIFER RABUCHIN |
| Final | 6/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 6/1/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/8/2023 | Approved | JENNIFER RABUCHIN |
| Final | 8/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 8/8/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/8/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/8/2023 | Approved | JENNIFER RABUCHIN |