13209 W DOBBINS PL 90049

Certificate Information: 13209 W DOBBINS PL 90049

Application / Permit
22010-20000-00769
Plan Check / Job No.
B22VN02479
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 91'10" X 59'6" TWO STORY IRREGULAR SHAPED SFD WITH ATTACHED TWO CAR GARAGE AND HABITABLE BASEMENT, NFPA-13D FIRE SPRINLERS REQUIRED THROGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/9/2023
Issuing Office
Current Status
CofO Issued on 7/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 RARES BODEA
Corrections Issued 4/11/2022 RARES BODEA
Quality Review Completed 4/14/2022 STEVEN KIM
Building Plans Picked Up 4/15/2022 APPLICANT
Applicant returned to address corrections 8/1/2022 RARES BODEA
Applicant returned to address corrections 8/2/2022 RARES BODEA
Plan Check Approved 8/31/2022 RARES BODEA
Issued 2/9/2023 APPLICANT
CofO in Progress 7/15/2024 ARAM AVEDISIAN
Permit Finaled 7/20/2024 DANIEL ORRANTE
CofO Issued 7/20/2024 DANIEL ORRANTE
Permit Finaled 7/20/2024 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 5/31/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 6/6/2022 ANTHONY MAINEZ
Sewer availability Cleared 6/6/2022 ANTHONY MAINEZ
Hydrant and Access approval Cleared 6/9/2022 LAVEON RIDER
Low Impact Development Cleared 6/22/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/27/2022 ANTHONY MAINEZ
GPI Written Notices Cleared 8/1/2022 RARES BODEA
Grading Pre-Inspection Cleared 8/1/2022 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/17/2023 Approved OGANES TARAKHCHYAN
Deputy Reinf. Concrete 2/23/2023 No Access for Inspection KENNETH NAGLE
Piling/Pier/Caisson 2/23/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 3/6/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 4/10/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/2/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 5/2/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/4/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/17/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 5/18/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 5/24/2023 Approved OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/25/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 7/28/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/31/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 9/6/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/3/2023 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/3/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 10/3/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/5/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 10/6/2023 Corrections Issued ARAM AVEDISIAN
Shower Pan 10/6/2023 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 10/12/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 10/12/2023 Approved ARAM AVEDISIAN
Shower Pan 10/12/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/13/2023 Corrections Issued OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 10/13/2023 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/23/2023 Corrections Issued OGANES TARAKHCHYAN
Green Building Rough 10/23/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 10/23/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/25/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 10/25/2023 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 10/25/2023 Approved OGANES TARAKHCHYAN
Insulation 10/26/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 10/30/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 11/13/2023 Approved ARAM AVEDISIAN
HVAC-Final 5/28/2024 Corrections Issued MICHAEL PELHAM
PLUMBING-Final 5/28/2024 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Final 6/12/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Final 6/12/2024 Approved ARAM AVEDISIAN
PLUMBING-Final 6/12/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Final 6/17/2024 Not Ready for Inspection ARAM AVEDISIAN
Green Building Final 6/17/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 6/17/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Final 7/2/2024 Approved KENNETH NAGLE
Final 7/15/2024 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 7/15/2024 Approved ARAM AVEDISIAN