11950 W SARAH ST 91607

Certificate Information: 11950 W SARAH ST 91607

Application / Permit
22010-20000-00763
Plan Check / Job No.
B22VN02431
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 43' X 37' 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, COVERED ROOF DECK ON 2ND FLOOR, AND ATTACHED TRELLIS. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/1/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 COLIN LOREDO
Corrections Issued 3/8/2022 COLIN LOREDO
Quality Review Completed 3/9/2022 OMID HEDAYAT
Building Plans Picked Up 3/10/2022 APPLICANT
Applicant returned to address corrections 5/3/2022 COLIN LOREDO
Plan Check Approved 8/1/2022 OMID HEDAYAT
Issued 8/1/2022 APPLICANT
CofO in Progress 10/24/2023 JUAN VALENZUELA
Permit Finaled 12/1/2023 RUBEN SALAS
CofO Issued 12/1/2023 RUBEN SALAS
Permit Finaled 12/1/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/25/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/25/2022 LEE GUILBEAUX
Permit Cleared 3/25/2022 LEE GUILBEAUX
Sewer availability Cleared 3/25/2022 LEE GUILBEAUX
Disturb/Remove Protected Trees Cleared 4/22/2022 ADALBERTO VERA
Trees in Parkway Cleared 4/22/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 5/6/2022 RUEL COLE
ZI Cleared 5/25/2022 MIGUEL GAMBOA
Low Impact Development Cleared 7/6/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/7/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Afzal,, Behzad; Lic. No.: C79628 22 CREEK RD 52      IRVINE, CA 92604

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/26/2022 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 10/19/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 3/30/2023 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 4/25/2023 Corrections Issued JACK KARGODORIAN
Green Building Rough 4/25/2023 Approved JACK KARGODORIAN
MERV13>=Rough 4/25/2023 Approved JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 4/25/2023 Corrections Issued JACK KARGODORIAN
Verify Sprinkler Sign Off 4/25/2023 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 5/2/2023 Corrections Issued JOHN COLEMAN
Interior/Exterior Lathing 5/2/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 5/2/2023 Approved JOHN COLEMAN
ELECTRICAL-Rough 5/30/2023 Approved JACK KARGODORIAN
Insulation 5/30/2023 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 5/30/2023 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 5/30/2023 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 5/30/2023 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 6/1/2023 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 6/9/2023 Approved JACK KARGODORIAN
Insulation 6/9/2023 Approved JACK KARGODORIAN
Wood Frame 6/9/2023 Not Ready for Inspection JACK KARGODORIAN
Drywall Nailing 6/20/2023 Approved JACK KARGODORIAN
Shower Pan 7/28/2023 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 9/22/2023 Not Ready for Inspection JACK KARGODORIAN
Final 9/22/2023 Corrections Issued JACK KARGODORIAN
Green Building Final 9/22/2023 Approved JACK KARGODORIAN
MERV13>=Final 9/22/2023 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/22/2023 SGSOV Not Ready JACK KARGODORIAN
Service/Power Release 9/22/2023 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 9/22/2023 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 9/22/2023 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 9/29/2023 Approved JACK KARGODORIAN
Final 9/29/2023 Corrections Issued JACK KARGODORIAN
MERV13>=Final 9/29/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved JACK KARGODORIAN
Service/Power Release 9/29/2023 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 9/29/2023 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 9/29/2023 Approved JACK KARGODORIAN
Final 10/6/2023 OK to Issue CofO JUAN VALENZUELA
Service/Power Release 10/6/2023 Approved JUAN VALENZUELA