10950 W VERANO ROAD 90077
Certificate Information: 10950 W VERANO ROAD 90077
- Application / Permit
- 22010-20000-00742
- Plan Check / Job No.
- B22VN02401
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | COLIN LOREDO |
| Corrections Issued | 2/28/2022 | COLIN LOREDO |
| Quality Review Completed | 3/2/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/3/2022 | APPLICANT |
| Applicant returned to address corrections | 9/9/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/7/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/19/2022 | NILOOFAR MEHRAIN |
| Issued | 12/20/2022 | APPLICANT |
| CofO in Progress | 2/10/2025 | MICHAEL PELHAM |
| Permit Finaled | 2/11/2025 | RICHARD STEINBACH |
| CofO Issued | 2/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/21/2022 | KHAING AYE |
| Address approval | Cleared | 4/16/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 4/16/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 4/16/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 4/16/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 4/16/2022 | STEVE MELGAR |
| Permit | Cleared | 4/16/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 4/19/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 4/27/2022 | LAURINDA MEADE |
| Trees in Parkway | Cleared | 5/6/2022 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 5/13/2022 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 7/28/2022 | RAYMOND MUGAMBWA |
| Disturb/Remove Protected Trees | Cleared | 8/30/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 12/19/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 12/19/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/28/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/3/2023 | No Access for Inspection | CHRISTOPHER WILSON |
| Underground Mechanical | 10/5/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | No Access for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/15/2023 | No Access for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/16/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/29/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 12/1/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 12/1/2023 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/1/2023 | Approved | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Conditional Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 3/5/2024 | Partial Approval | CHRISTOPHER WILSON |
| Gas Test | 3/7/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Test | 3/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Test | 3/13/2024 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 3/13/2024 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 3/28/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 3/29/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/29/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 3/29/2024 | Corrections Issued | MICHAEL PELHAM |
| Shower Pan | 3/29/2024 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 4/1/2024 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 4/2/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 4/4/2024 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 4/4/2024 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 4/9/2024 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 4/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 4/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 4/11/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/15/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 5/8/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 5/8/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/8/2024 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 5/14/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/14/2024 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 5/21/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/21/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 5/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 6/4/2024 | Partial Approval | CHRISTOPHER WILSON |
| Final | 6/4/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/4/2024 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 6/4/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 10/4/2024 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 10/25/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 11/7/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 11/14/2024 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 11/14/2024 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 12/31/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 12/31/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 1/27/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 1/27/2025 | Approved | CHRISTOPHER WILSON |
| Final | 1/27/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Test | 1/27/2025 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 1/27/2025 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 1/27/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 1/27/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 1/27/2025 | Approved | CHRISTOPHER WILSON |
| Verify Rec and Parks Fee Memo | 1/27/2025 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 1/29/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Drywall Nailing | 2/6/2025 | Approved | CHRISTOPHER WILSON |
| Final | 2/6/2025 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 2/6/2025 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 2/6/2025 | Approved | CHRISTOPHER WILSON |
| Final | 2/10/2025 | OK to Issue CofO | MICHAEL PELHAM |