5850 N PENFIELD AVE 91367

Certificate Information: 5850 N PENFIELD AVE 91367

Application / Permit
22010-20000-00740
Plan Check / Job No.
B22VN02398
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW DETACHED 1-STORY 79' X 60'-1" IRREGULAR SHAPED ACCESSORY LIVING QUARTERS. NFPA 13D FIRE SPRIKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/3/2022
Issuing Office
Valley
Current Status
Issued on 11/3/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 COLIN LOREDO
Corrections Issued 2/28/2022 COLIN LOREDO
Building Plans Picked Up 3/1/2022 APPLICANT
Quality Review Completed 3/2/2022 OMID HEDAYAT
Applicant returned to address corrections 7/14/2022 COLIN LOREDO
Plan Check Approved 7/22/2022 COLIN LOREDO
Issued 11/3/2022 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/5/2022 LAURINDA MEADE
Low Impact Development Cleared 5/3/2022 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 5/4/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 5/4/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/4/2022 DAGOVERTO GUERRERO
Watercourse Cleared 6/27/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 7/14/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 7/14/2022 COLIN LOREDO
Miscellaneous Cleared 10/3/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/13/2023 Approved JON MCHUGH
Underground Mechanical 3/13/2023 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 3/28/2023 Approved JON MCHUGH
Footing/Foundation/Slab 3/28/2023 Approved JON MCHUGH
ELECTRICAL-Rough 10/4/2023 Approved JON MCHUGH
HVAC-Rough 10/4/2023 Conditional Approval JON MCHUGH
BUILDING-Rough-Frame 10/27/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval JON MCHUGH
Green Building Rough 10/27/2023 Not Ready for Inspection JON MCHUGH
Verify Sprinkler Sign Off 10/27/2023 Partial Approval JON MCHUGH
Interior/Exterior Lathing 12/4/2023 Partial Approval MORRIS JACKSON
Shower Pan 12/4/2023 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 1/3/2024 Approved JON MCHUGH
Green Building Rough 1/3/2024 Approved JON MCHUGH
Insulation 1/3/2024 Approved JON MCHUGH
Rough-Elec/Plmb/HVAC 1/3/2024 Approved JON MCHUGH
Verify Sprinkler Sign Off 1/3/2024 Approved JON MCHUGH
Drywall Nailing 1/16/2024 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 1/16/2024 Partial Approval JON MCHUGH
Drywall Nailing 1/31/2024 Approved HENRY KIM