5464 W CARLIN ST 90016
Certificate Information: 5464 W CARLIN ST 90016
- Application / Permit
- 22010-20000-00736
- Plan Check / Job No.
- B22VN02377
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-6" X 26'-6" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/25/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | SELLA BENYAMIN |
| Corrections Issued | 3/18/2022 | SELLA BENYAMIN |
| Quality Review Completed | 3/24/2022 | STEVEN KIM |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Plan Check Approved | 7/21/2022 | SELLA BENYAMIN |
| Issued | 7/25/2022 | APPLICANT |
| CofO in Progress | 5/12/2023 | JOSE AVILA |
| Permit Finaled | 5/20/2023 | DEROLD HAUFF |
| CofO Issued | 5/20/2023 | DEROLD HAUFF |
| Permit Finaled | 5/20/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 6/3/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/21/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 6/29/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/7/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/28/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/28/2022 | Partial Approval | STUART CHAPMAN |
| Sewer | 8/4/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2022 | Approved | JOSE AVILA |
| Green Building Rough | 8/15/2022 | Not Ready for Inspection | JOSE AVILA |
| Verify Sprinkler Sign Off | 8/15/2022 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 10/5/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 10/5/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 10/17/2022 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 10/17/2022 | Approved | JOSE AVILA |
| Green Building Rough | 10/17/2022 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 10/17/2022 | Conditional Approval | JOSE AVILA |
| Deputy Wood Construction | 10/18/2022 | Conditional Approval | JOSE AVILA |
| Insulation | 10/21/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/21/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 10/26/2022 | Conditional Approval | JOSE AVILA |
| Special/Order Compliance | 10/26/2022 | Corrections Issued | JOSE AVILA |
| Shower Pan | 11/30/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/3/2023 | Approved | JOSE AVILA |
| Final | 3/3/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 3/3/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/3/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 3/3/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 3/3/2023 | Approved | JOSE AVILA |
| Final | 4/13/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 4/13/2023 | Approved | JOSE AVILA |
| Service/Power Release | 4/13/2023 | Approved | JOSE AVILA |
| Final | 4/19/2023 | Corrections Issued | JOSE AVILA |
| Final | 5/11/2023 | OK to Issue CofO | JOSE AVILA |