3848 N VANTAGE AVE 91604

Certificate Information: 3848 N VANTAGE AVE 91604

Application / Permit
22010-20000-00725
Plan Check / Job No.
B22VN02337
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (71'-3"x 30'-0") 2-STORY IRR SHAPE SINGLE FAMILY DWELLING W/ATT 2-CAR GARAGE, NFPA-13D AUTO FIRE SPRINKLER THRUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 4/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 TROY DEGUZMAN
Corrections Issued 3/16/2022 TROY DEGUZMAN
Quality Review Completed 3/25/2022 OMID HEDAYAT
Building Plans Picked Up 3/31/2022 APPLICANT
Applicant returned to address corrections 10/12/2022 PETER MOSESIAN
Plan Check Approved 11/4/2022 PETER MOSESIAN
Issued 4/6/2023 APPLICANT
CofO in Progress 11/19/2025 CHRISTOPHE COCHRAN
No Progress 1/15/2026 RAUL OLAGI
CofO in Progress 1/15/2026 RAUL OLAGI
CofO Issued 3/26/2026 RUBEN SALAS
Permit Finaled 3/26/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/14/2022 TIMOTHY POWELL
Address approval Cleared 6/10/2022 CARLOS AGUILERA
Low Impact Development Cleared 6/21/2022 SUNG JOON WON
Hydrant and Access approval Cleared 8/3/2022 LAVEON RIDER
Eng Process Fee Ord 176,300 Cleared 8/9/2022 CARLOS AGUILERA
Sewer availability Cleared 8/9/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/10/2022 ROMAN GUTIERREZ
ZI Cleared 8/30/2022 RUBEN VASQUEZ
Green Code Cleared 11/2/2022 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/18/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 4/18/2023 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 5/12/2023 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/12/2023 Approved CHRISTOPHE COCHRAN
Grounding or Bonding 5/12/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval CHRISTOPHE COCHRAN
Gas Test 8/1/2023 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 8/1/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/1/2023 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 8/1/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/8/2023 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/8/2023 Approved CHRISTOPHE COCHRAN
HVAC-Rough 11/8/2023 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 11/8/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/15/2023 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 12/27/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/27/2023 Approved CHRISTOPHE COCHRAN
HVAC-Rough 12/27/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/27/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 12/27/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 12/27/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 1/3/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 1/3/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/8/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 3/22/2024 Approved CHRISTOPHE COCHRAN
Final 10/30/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 10/30/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 10/30/2025 Approved CHRISTOPHE COCHRAN
Smoke Detectors 10/30/2025 Approved CHRISTOPHE COCHRAN
Final 11/19/2025 OK to Issue CofO CHRISTOPHE COCHRAN